Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Vizianagram)
|
EDS
|
User Agency (ee_piu_vznm@yahoo.com)
|
12/07/2021
|
The 6 sets of proposals hard copies are returned herewith for rectification and re submission to this office at the earliest.
|
|
2
|
User Agency (ee_piu_vznm@yahoo.com)
|
REPLY
|
DFO (Vizianagram)
|
15/07/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Vizianagram)
|
EDS
|
User Agency (ee_piu_vznm@yahoo.com)
|
24/09/2021
|
The CA land details are not furnished by the User Agency. Hence the proposals are returned to the User Agency.
|
|
4
|
User Agency (ee_piu_vznm@yahoo.com)
|
REPLY
|
DFO (Vizianagram)
|
26/02/2022
|
The correction have been made as per the instruction received
|
|
5
|
CF (Visakhapatnam)
|
EDS
|
DFO (Vizianagram)
|
07/03/2022
|
The DFO, Viizianagaram is requested to submit proposals along with CA scheme.
|
|
6
|
DFO (Vizianagram)
|
REPLY
|
CF (Visakhapatnam)
|
14/03/2022
|
The Government of India have insisted to obtain CA land from the user agency. Hence on receipt of CA land from the user agency, this CA Scheme prepared and re-submitted herewith.
|
|
7
|
CF (Visakhapatnam)
|
EDS
|
DFO (Vizianagram)
|
17/03/2022
|
The DFO vzm is requested to re submit/upload the Part II proposals with rectified information and connected documents.
|
|
8
|
DFO (Vizianagram)
|
REPLY
|
CF (Visakhapatnam)
|
17/03/2022
|
CA site inspection notes, details and CA Scheme, data sheets, Collector proceedings, approved CA Scheme by the CCF, VSP etc. enclosed herewith
|
|
9
|
CF (Visakhapatnam)
|
EDS
|
DFO (Vizianagram)
|
21/03/2022
|
The DFO, Vizianagaram is requested to re-submit the proposal with rectified information on certain issues.
|
|
10
|
DFO (Vizianagram)
|
REPLY
|
CF (Visakhapatnam)
|
21/03/2022
|
Revised Part-II submitted
|
|