TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AP/ROAD/11459/2015              (ii). Name of Project for which Forest Land is required : Improvements to Araku Valley to Panchipenta road from Working Reach Km 24/0 to 35/0              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Improvements to the road from Km 24/0 to 42/0 of Araku valley to Panchipenta (via) Lotheru-Aluru in Visakhapatnam District.(Working Reach Km 24/0 to 35/0), NABARD Scheme              (iv). File no. : G.O.Rt.No.34              (v). State : Andhra Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 4.5
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/AP/ROAD/11459/201503/04/2015aa17/06/2015   20/06/2015 Visakhapatnam :22/06/2015Visakhapatnam:
  04/11/2015 (Visakhapatnam)

Andhra Pradesh:
09/11/2015
Andhra Pradesh:
13/05/2016
15/03/2018
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Andhra Pradesh) on:19/06/2017  
Replied by Nodal Officer (Andhra Pradesh) on:03/10/2017  
Query raised by Nodal Officer (Andhra Pradesh) on:19/06/2017  
Replied by Circle(Visakhapatnam) on:19/09/2017  
Query raised by Circle (Visakhapatnam) on:19/06/2017  
Replied by DFO (Visakhapatnam) on:19/08/2017  
Query raised by Circle (Visakhapatnam) on:19/09/2017  
Replied by DFO (Visakhapatnam) on:19/09/2017  
NOTE:- Stage-I Approval accorded by : State Government .