Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Narasipatnam)
|
EDS
|
User Agency (eeprpdr2010@gmail.com)
|
30/01/2021
|
The EE, PRI, Paderu is requested to submit RoFR certificate for processing the proposal
|
|
2
|
User Agency (eeprpdr2010@gmail.com)
|
REPLY
|
DFO (Narasipatnam)
|
28/02/2021
|
The correction have been made as per the instruction received
|
|
3
|
State secretary
|
EDS
|
Nodal Officer
|
21/06/2021
|
Requested to identify suitable non forest area for compensatory afforestation.
|
|
4
|
Nodal Officer
|
EDS
|
CF (Visakhapatnam)
|
12/07/2021
|
Request to furnish CA land details
|
|
5
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
14/07/2021
|
The DFO Narsipatnam is requested to re-submit the proposals along with non-forest land identified for CA
|
|
6
|
DFO (Narasipatnam)
|
EDS
|
User Agency (eeprpdr2010@gmail.com)
|
14/07/2021
|
The Executive Engineer, PR Division, Paderu is requested to submit CA land details as called for by the Prl.CCF&HoFF, A.P., Guntur for further process.
|
|
7
|
User Agency (eeprpdr2010@gmail.com)
|
REPLY
|
DFO (Narasipatnam)
|
22/01/2022
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Narasipatnam)
|
EDS
|
User Agency (eeprpdr2010@gmail.com)
|
15/02/2022
|
The Executive Engineer, PR PIU Division, Paderu is requested to submit the reports on each road proposal to concerned Divisional Forest Officers along with all necessary documents i.e. CA area soil/ site suitability certificate, authenticated DGPS map, kml file and Proceedings of the District Collector, Visakhapatnam in 6 sets in hard and soft copies to process the road proposals for further process.
|
|
9
|
User Agency (eeprpdr2010@gmail.com)
|
REPLY
|
DFO (Narasipatnam)
|
18/02/2022
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
18/02/2022
|
The report along with CA land details submitted herewith for further process.
|
|
11
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
22/02/2022
|
The DFO, Narsipatnam is requested to submit proposal along with revised CA scheme details
|
|
12
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
24/02/2022
|
The Part-II proposals are submitted along with revised CA Scheme details for further process.
|
|
13
|
CF (Visakhapatnam)
|
REPLY
|
Nodal Officer
|
24/02/2022
|
The DFO, Narsipatnam and CCF, Visakhapatnam recommended the proposal, along with CA
|
|
14
|
Nodal Officer
|
EDS
|
CF (Visakhapatnam)
|
03/03/2022
|
Request to attend on shortcomings
|
|
15
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
03/03/2022
|
The DFO, Narsipatnam is requested to submit rectified proposals as per the shortcomings communicated by the Nodal Officer
|
|
16
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
03/03/2022
|
The shortcomings and proportionate CA scheme details are uploaded and requested for taking further process.
|
|
17
|
CF (Visakhapatnam)
|
REPLY
|
Nodal Officer
|
04/03/2022
|
As per the instructions issued by the Nodal Officer, rectified proposals along with CA details are uploaded.
|
|
18
|
Nodal Officer
|
REPLY
|
State secretary
|
07/03/2022
|
Ca land details submitted
|
|