Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kurnool)
|
EDS
|
User Agency (dycecngtl@gmail.com)
|
01/05/2022
|
RoFR Certificate in Form-I
|
|
2
|
User Agency (dycecngtl@gmail.com)
|
REPLY
|
DFO (Kurnool)
|
02/05/2022
|
The correction have been made as per the instruction received
|
|
3
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
07/06/2022
|
Proposals returned
|
|
4
|
DFO (Kurnool)
|
EDS
|
User Agency (dycecngtl@gmail.com)
|
07/06/2022
|
Resubmit the proposals called for Reg
|
|
5
|
User Agency (dycecngtl@gmail.com)
|
REPLY
|
DFO (Kurnool)
|
23/08/2022
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
25/08/2022
|
Proposals resubmitted -Reg
|
|
7
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
13/09/2022
|
Proposals returned for resubmission
|
|
8
|
DFO (Kurnool)
|
EDS
|
User Agency (dycecngtl@gmail.com)
|
16/09/2022
|
Proposals returned for resubmission
|
|
9
|
User Agency (dycecngtl@gmail.com)
|
REPLY
|
DFO (Kurnool)
|
25/11/2022
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
25/11/2022
|
The user agency has submitted the replies for the queries raised by the Conservator of Forests, Kurnool Circle, Kurnool along with six (6) of proposals booklets etc submitted herewith
|
|
11
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
28/11/2022
|
Returned for resubmission
|
|
12
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
05/12/2022
|
Documents uploaded for the queries raised - Additional information submission Reg
|
|
13
|
Nodal Officer
|
EDS
|
CF (Kurnool)
|
09/01/2023
|
Additional information requested
|
|
14
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
09/01/2023
|
Additional Information called for
|
|
15
|
DFO (Kurnool)
|
EDS
|
User Agency (dycecngtl@gmail.com)
|
09/01/2023
|
Submit the re-diversion proposal for the forest area falling between stretches 3 to 8 -Additional information called for -Reg
|
|
16
|
User Agency (dycecngtl@gmail.com)
|
REPLY
|
DFO (Kurnool)
|
11/01/2023
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
27/01/2023
|
additional information uploaded -Reg
|
|
18
|
CF (Kurnool)
|
REPLY
|
Nodal Officer
|
30/01/2023
|
Rediversion proposals for forest area falling between the stretches 3 to 8
|
|
19
|
Nodal Officer
|
EDS
|
CF (Kurnool)
|
06/02/2023
|
Requires certain additional information
|
|
20
|
CF (Kurnool)
|
EDS
|
DFO (Kurnool)
|
06/02/2023
|
Short comings observed additional information called for
|
|
21
|
DFO (Kurnool)
|
EDS
|
User Agency (dycecngtl@gmail.com)
|
06/02/2023
|
Short comings observed additional information called for
|
|
22
|
User Agency (dycecngtl@gmail.com)
|
REPLY
|
DFO (Kurnool)
|
25/05/2023
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Kurnool)
|
REPLY
|
CF (Kurnool)
|
26/05/2023
|
short comings observed additional information submission by the user agency
|
|
24
|
CF (Kurnool)
|
REPLY
|
Nodal Officer
|
26/05/2023
|
Additional information submission
|
|