| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
CF (Guntur)
|
EDS
|
DFO (Guntur)
|
26/02/2019
|
RoFR Certificate from the District Administration is not enclosed to the proposals.
|
|
|
2
|
DFO (Guntur)
|
EDS
|
User Agency (rayudubt@gmail.com)
|
08/08/2019
|
RoFR Certificate from the District Administration is not enclosed to the proposals. Hence he is requested to furnish the same immediately
|
|
|
3
|
User Agency (rayudubt@gmail.com)
|
REPLY
|
DFO (Guntur)
|
14/07/2023
|
The correction have been made as per the instruction received
|
|
|
4
|
DFO (Guntur)
|
REPLY
|
CF (Guntur)
|
14/07/2023
|
Additional Information with regard to RoFR details sent with a request to process the proposals under Section 2 of Forest (Conservation)Act,1980
|
|