TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AP/OFC/148408/2021              (ii). Name of Project for which Forest Land is required : Laying of Optical Fibre Cable (OFC) along existing Right of Way of the Roads passing through Forests under Proddatur WL Division              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of underground Optical Fibre Cable (OFC) between Badvel and Padamatinaidupalle villages within the existing Right of Way (RoW) of Roads passing through Forest land under Proddatur WL Division for providing 4G communications in Cuddapah District of Andhra Pradesh              (iv). File no. : 1769/Section-II/2023              (v). State : Andhra Pradesh              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.36
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/AP/OFC/148408/202121/10/202116/12/2021  03/11/2021   17/12/2021  26/11/2021   10/01/2022   09/03/2022 Proddatur (WL) :16/03/2022Kurnool:
  20/07/2023 (Proddatur (WL))

Andhra Pradesh:
20/07/2023
Andhra Pradesh:
07/08/2023
23/08/2023
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Proddatur (WL)) on:19/05/2022  
Replied by UA on :29/09/2022  
Query raised by DFO (Proddatur (WL)) on:18/10/2022  
Replied by UA on :13/07/2023  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
   Query raised by State Government (Andhra Pradesh) on:24/03/2025  
Query raised by Nodal Officer on:02/06/2025  
NOTE:- Proposal is pending at User Agency due to EDS raised by State Government for verifying Compliance of Conditions .