Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (WL Chittoor East)
|
EDS
|
User Agency (cetgpskht@yahoo.co.in)
|
09/10/2018
|
Construction of somasila Swarnamukhi
|
|
2
|
User Agency (cetgpskht@yahoo.co.in)
|
REPLY
|
DFO (WL Chittoor East)
|
14/10/2018
|
The correction have been made as per the instruction received
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
25/01/2019
|
Additional information related to violation is required
|
|
4
|
State secretary
|
EDS
|
Nodal Officer
|
02/05/2019
|
Required Additional Information
|
|
5
|
Nodal Officer
|
REPLY
|
State secretary
|
02/05/2019
|
Additional Infirmation
|
|
6
|
State secretary
|
REPLY
|
Regional Office
|
02/05/2019
|
Additional Information Furnished
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
19/06/2019
|
Requested to furnish the information/documents as sought by the REC
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
15/03/2020
|
Request to furnish the information
|
|
9
|
Nodal Officer
|
EDS
|
CF (Guntur)
|
17/03/2020
|
Information requested by government
|
|
10
|
Nodal Officer
|
EDS
|
CF (WLM - Tirupathi)
|
17/03/2020
|
Information requested by government
|
|
11
|
CF (Guntur)
|
REPLY
|
Nodal Officer
|
27/10/2020
|
Sir, submitted reply on EDS raised by the Government.
|
|
12
|
CF (WLM - Tirupathi)
|
REPLY
|
Nodal Officer
|
15/12/2020
|
Additional infomation attached
|
|
13
|
Nodal Officer
|
REPLY
|
State secretary
|
16/12/2020
|
Additional information submitted
|
|
14
|
State secretary
|
REPLY
|
Regional Office
|
16/12/2020
|
Additional information submitted
|
|
15
|
State secretary
|
REPLY
|
Regional Office
|
16/12/2020
|
Additional information submitted
|
|