| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Nodal Officer
|
EDS
|
CF (Rajahmundry)
|
25/06/2016
|
Kindly upload the Part-II of recommendation.
|
|
|
2
|
CF (Rajahmundry)
|
EDS
|
DFO (Eluru)
|
25/06/2016
|
Kindly upload the Part-II Recommendation letter.
|
|
|
3
|
DFO (Eluru)
|
REPLY
|
CF (Rajahmundry)
|
06/07/2016
|
Sir, we uploaded the rectified re uploaded the proposal
|
|
|
4
|
CF (Rajahmundry)
|
REPLY
|
Nodal Officer
|
06/07/2016
|
Sir, we uploaded the rectified re uploaded the proposal
|
|
|
5
|
Head Office
|
EDS
|
State secretary
|
04/11/2016
|
EDS
|
|
|
6
|
State secretary
|
REPLY
|
Head Office
|
20/03/2017
|
I enclose herewith the letter along with the enclosures received from the PCCF(HoFF),A.P., with a request to obtain and communicate the approval of Govt.of India, Ministry of Environment,Forests&Climate Change,under Section 2 of FC Act, 1980 for the above four projects, at an early date.
|
|