| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Nodal Officer
|
EDS
|
CF (Visakhapatnam)
|
04/07/2017
|
It is requested to attend to the shortcomings mentioned in the attached letter for taking further necessary action in processing the proposal.
|
|
|
2
|
CF (Visakhapatnam)
|
EDS
|
DFO (Vizianagram)
|
04/07/2017
|
It is requested to attend to the shortcomings mentioned in the attached letter for taking further necessary action in processing the proposal.
|
|
|
3
|
DFO (Vizianagram)
|
REPLY
|
CF (Visakhapatnam)
|
16/01/2018
|
Submitted to the detailed report in Hydel project
|
|
|
4
|
CF (Visakhapatnam)
|
EDS
|
DFO (Vizianagram)
|
17/01/2018
|
submission of rectified proposal as submitted by the DFO, Vizianagaram
|
|
|
5
|
DFO (Vizianagram)
|
EDS
|
User Agency (umrao@mohanarupapower.com)
|
06/02/2018
|
Submitted to the CF
|
|
|
6
|
User Agency (umrao@mohanarupapower.com)
|
REPLY
|
DFO (Vizianagram)
|
27/03/2018
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Vizianagram)
|
EDS
|
User Agency (umrao@mohanarupapower.com)
|
29/03/2018
|
submission of rectified proposal as submitted by the DFO, Vizianagaram
|
|
|
8
|
User Agency (umrao@mohanarupapower.com)
|
REPLY
|
DFO (Vizianagram)
|
29/03/2018
|
The correction have been made as per the instruction received
|
|
|
9
|
DFO (Vizianagram)
|
REPLY
|
CF (Visakhapatnam)
|
29/03/2018
|
Submission of rectified proposal as submitted by the DFO, Vizianagaram
|
|
|
10
|
CF (Visakhapatnam)
|
EDS
|
DFO (Vizianagram)
|
26/05/2018
|
Rectified proposals submitted
|
|
|
11
|
DFO (Vizianagram)
|
REPLY
|
CF (Visakhapatnam)
|
31/05/2018
|
Sir, submission of rectified proposals as submitted by the DFO, Vizianagaram
|
|
|
12
|
CF (Visakhapatnam)
|
REPLY
|
Nodal Officer
|
01/08/2018
|
Query Reply
|
|
|
13
|
Regional Office
|
EDS
|
State secretary
|
07/02/2020
|
to furnish the additional information/ documents to this office
|
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
16/06/2020
|
Comments on the remarks of the Water source Dept.
|
|
|
15
|
Nodal Officer
|
REPLY
|
State secretary
|
22/06/2020
|
Additional information submitted
|
|
|
16
|
State secretary
|
REPLY
|
Regional Office
|
17/11/2020
|
Additional information submitted
|
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
07/04/2021
|
as per attached EDS
|
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
19/04/2021
|
Additional information
|
|
|
19
|
Nodal Officer
|
EDS
|
CF (Visakhapatnam)
|
28/04/2021
|
Further Information called for
|
|
|
20
|
CF (Visakhapatnam)
|
EDS
|
DFO (Vizianagram)
|
15/05/2021
|
DFO, Vizianagaram is requested to submit further information as called for by the Prl. CCF
|
|
|
21
|
DFO (Vizianagram)
|
EDS
|
User Agency (umrao@mohanarupapower.com)
|
16/06/2021
|
The User Agency requested to submit the musk disposal plan
|
|
|
22
|
User Agency (umrao@mohanarupapower.com)
|
REPLY
|
DFO (Vizianagram)
|
16/06/2021
|
The correction have been made as per the instruction received
|
|
|
23
|
DFO (Vizianagram)
|
EDS
|
User Agency (umrao@mohanarupapower.com)
|
12/07/2021
|
The user agency has submitted to the Musk Disposal Plan, but the location map in ARC VIEW, Survey of India sheet and KML file could not furnished to this office. 7 Sets of location map in ARC VIEW, Survey of India Sheet and KML file for the said Hydel Project to this office for countersigned.
|
|
|
24
|
User Agency (umrao@mohanarupapower.com)
|
REPLY
|
DFO (Vizianagram)
|
16/07/2021
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Vizianagram)
|
REPLY
|
CF (Visakhapatnam)
|
29/07/2021
|
The proposed musk disposal area is outside to the Nanda Reserved Forest and location in the power project area under the control of the user agency.
|
|
|
26
|
CF (Visakhapatnam)
|
REPLY
|
Nodal Officer
|
21/08/2021
|
It is submitted that, as per the reports submitted by the DFO, Vizianagaram, muck disposal
plant is submitted herewith for necessary action.
|
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
16/09/2021
|
Further Information Submitted.
|
|
|
28
|
State secretary
|
REPLY
|
Regional Office
|
27/09/2021
|
Additional Information submitted
|
|