TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AP/HYD/35371/2018              (ii). Name of Project for which Forest Land is required : Pumped Storage Component of Pinnapuram IREP              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The GoAP has approved the project with First Right of Refusal to utilize the energy from the project, however with no obligation to consume the same. This Project report is for the standalone Pumped Storage component of IREP of 1200 MW storage capacity, located at Kurnool District, Andhra Pradesh.              (iv). File no. : 8-32/2019-FC              (v). State : Andhra Pradesh              (vi). Category of the Project : Hydel              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 365.66
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/AP/HYD/35371/201828/08/2018aa10/09/2018   10/09/2018 Kurnool :10/09/2018Kurnool:
  31/05/2019 (Kurnool)

Andhra Pradesh:
04/06/2019
Andhra Pradesh:
08/06/2019
15/11/201905/12/2019
17/01/2020
23/04/2020
By :Head Office
Andhra Pradesh
19/04/2021
24/05/2021
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by Circle (Kurnool) on:04/06/2019  
Replied by DFO (Kurnool) on:04/06/2019  
Query raised by DFO (Kurnool) on:30/05/2019  
Replied by UA on :30/05/2019  
NOTE:- Stage-II Approval accorded by : Head Office .