TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/HYD/6201/2022   (ii). Name of Project for which Forest Land is required : JIMBAGAD SMALL HYDRO PROJECT (3X4 MW)   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : IT IS A RUN OFF RIVER SCHEME. ANUUAL ENERGY GENERATION FROM THE PROJECT IS 62.32 M.U. PROJECT IS LOCATED ON JIMBA STREAM A TRIBUTARY OF RIVER GORIGANGA.   (iv). State : Uttarakhand   (v). Category of the Project : Hydel   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Area of forest land proposed for diversion(in ha.): NIL
B. Time Line
Submitted by User AgencyQuery for Shortcoming(if any) by Wildlife WardenResubmission of Proposal by User AgencyQuery by Wildlife Warden for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from Wildlife WardenWildlife WardenChief Wildlife WardenState Government/SBWLFinal Disposal
21/05/202219/05/2022   20/05/2022   21/05/2022   21/05/2022 Pithoragarh :28/05/2022Uttarakhand (Pithoragarh):  09/06/2022
C Essential Details Sought History
Communication between MoEFCC(WL),New Delhi & State GovernmentCommunication between State Government & Chief Wildlife WardenCommunication between Chief Wildlife Warden & Wildlife WardenCommunication between Wildlife Warden & User Agency
  Query raised by Chief Wildlife Warden (Uttarakhand) on:08/09/2022  
Replied by Wildlife Warden(North Kumaun) on:19/01/2023  
Query raised by Chief Wildlife Warden (Uttarakhand) on:02/03/2023  
Replied by Wildlife Warden(North Kumaun) on:26/05/2025  
Query raised by Chief Wildlife Warden (Uttarakhand) on:02/01/2025  
Replied by Wildlife Warden(North Kumaun) on:23/12/2024  
Query raised by Wildlife Warden (Pithoragarh) on:12/09/2022  
Replied by UA on :05/12/2022  
NOTE:- Proposal is pending at Chief Wildlife Warden .