A. General Details
  (i). Proposal No. : FP/OR/Others/152380/2022   (ii). Name of Project for which Forest Land is required : Diversion of 60.508 Ha virgin forest land under section 2(iii) of Forest Conservation Act, 1980 for assignment of mining lease in respect of Dholtapahar Iron ore block of M/s Kashvi Power & Steel Pvt.   (iii). State : Orissa   (iv). Category of the Project : Others   (v). Shape of forest land proposed to be diverted : Non Linear   (vi). Area of forest land proposed for diversion(in ha.): 60.508
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from Nodal OfficerNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onStage-II Approval on
FP/OR/Others/152380/202214/02/202204/03/2022   08/03/2022 Bonai :14/03/2022Orissa:
16/03/2023
31/03/2023
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 28/04/2023  
Replied by State Government (Orissa) on:02/08/2023  
Query raised by State Government (Orissa) on:09/05/2023  
Replied by Nodal Officer (Orissa) on:01/08/2023  
NOTE:- Proposal is pending at REJECTED .