TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JH/MIN/22525/2016   (ii). Name of Project for which Forest Land is required : DIRSUMBURU IRON ORE MINE IN KODOLIOBAD RESERVE FOREST OF SARANDA FOREST DIVISION BY ELECTROSTEEL CASTINGS LIMITED (ECL) (192.50 ha of forest land within Mining Lease including safety zone. Stage-I clearance available on part of forest area of Mining Lease i.e. 55.79 ha comprising 50.98 ha forest within Mining Lease and 4.81 ha outside ML)   (iii). State : Jharkhand   (iv). Category of the Project : Mining   (v). Shape of forest land proposed to be diverted : Non Linear   (vi). Area of forest land proposed for diversion(in ha.): 192.5
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from Nodal OfficerNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onStage-II Approval on
FP/JH/MIN/22525/201623/11/201628/11/2016   29/11/2016   01/12/2016   02/12/2016 Saranda :02/12/2016Jharkhand:
15/12/2016
21/12/201626/12/2016
04/01/2017
25/09/2017
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by State Government (Jharkhand) on:19/12/2016  
Replied by Nodal Officer (Jharkhand) on:21/12/2016  
NOTE:- Proposal Rejected by Head Office .