PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : UK-0266/2018
1. Location of the project/Scheme : Uttarakhand
 (i) State / Union Territory : Uttarakhand  (ii) District : Uttarkashi  (iii) Forest Division : Uttarkashi  (iv) Area of forest land proposed for diversion (in ha.) : 1.316  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Uttarkashi1.316Civil Soyam land
Total 1.316
Division 1. : Uttarkashi
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Uttarkashi1.316
Total1.316
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
11.3160.3Eco 5
Total. 1.316


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Rhododendron arboreumburansh222401
2Celtis australiskhadik146444
3Misc. Specieskemu011030
4Misc. Speciestitrai665500
5Alnus Nepalensisutis0012211
6Misc. Speciesanyar224634
7Misc. Speciessedi000101
8Misc. Speciesbhangsi000002
9Misc. Speciesrois001100
10Misc. Speciessurai111000
11Juglan Regiaakhrot000121
12Misc. Speciesbhangasi020000
13Pinus wallichianakail304235
14Misc. Speciesfaldar022000
15Misc. Speciesbhimal000300
Total 15 2027 2917 29
Sub Total (No of Trees.) 137


5. Working plan prescription for the forest land proposed for diversion : Not applicable
6. Brief note on vulnerability of the forest area to erosion : The area is geographically suitable as per the report
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.500
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Leopard,black bear etc.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : Yes
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1UttarkashiEid gaon2.6322852
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Additional information Details
S. No. DocumentsRemarks
1 S.I.R.
2 CA area suitability
3 trees list
4 Land schedule
5 Bar chart
6 NPV
7 New CA scheme
8 District profile

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Uttarkashi801600.00695783.351652.435522241.0830/06/20191990.748213.17
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
 BhagirathiCFNoNo Data
UttarkashiBhagirathiDFOYesOne04/07/2019
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
UttarkashiBhagirathiDFO Recommendedyes
BhagirathiCF RecommendedTo facilitate local villagers for road and communication.Yes
Nodal Officer RecommendedAs per file attached
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
UttarakhandState SecretaryRecommended25/02/2020 as per file attached State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
DehradunRegional Office8B/UCP/06/31/2020/FC09/10/2020
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/UK/ROAD/34286/2018ROAD342862018914175208017520802021-02-23PUNB205318864807Corporation BankNEFT/RTGS (Challan)2020-12-272021-01-01
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 2.632   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)2.632
  Status of CA Land so identified : Non Forest Area   Site Name : eid gaon dunda   Location Details : eid gaon dunda   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
BhagirathiUttarkashiDunda539618 Jun 20212.632
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/UK/ROAD/34286/201821 Oct 2021No DataAs per file attached
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/UK/ROAD/34286/201801 May 2024
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/UK/ROAD/34286/201824 Nov 2021EDS: State Govt. may attend the following shortcomings as per the attachment here 27 Dec 2021
FP/UK/ROAD/34286/201830 Jan 2023EDS: State govt. may attend the following shortcomings as per the attachment here 28 Apr 2023
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/UK/ROAD/34286/201815 Dec 2021
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/UK/ROAD/34286/2018Approved In-PrincipleNo Data