PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : UK-0229/2016
1. Location of the project/Scheme : Uttarakhand
 (i) State / Union Territory : Uttarakhand  (ii) District : Bageshwar  (iii) Forest Division : Bageshwar  (iv) Area of forest land proposed for diversion (in ha.) : 2.68  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Bageshwar1.386Revenue Forest
2Bageshwar1.172Village Forest
3Bageshwar0.122Reserved Forest
Total 2.68
Division 1. : Bageshwar
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Bageshwar2.68
Total2.68
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
12.680.01Eco 5
Total. 2.68


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Pinus roxburghiichir0272114135
2Otherskukat010010
3Quercus leucotricophorabaanz008600
Total 0 2829 2014 5
Sub Total (No of Trees.) 96


5. Working plan prescription for the forest land proposed for diversion : pungar comp 9,chior working circle,quality class II/III P.B.Last.due to public requirement road has been proposed in the forest land to be diverted.
6. Brief note on vulnerability of the forest area to erosion : area is prone to soil erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.00
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : wildlife presence is rare in the forest land proposed for diversion.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1BageshwarGason5.362
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Additional information Details
S. No. DocumentsRemarks
NIL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Bageshwar231000107400726.604153721453.208315/07/20161356.000.00
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
BageshwarNorth KumaunDFOYesOne14/07/2016
 North KumaunCFNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
BageshwarNorth KumaunDFO Recommended
North KumaunCF RecommendedThe Proposal is in Public Interest. As per Proposal population 242 of 1 villages will be benefited hence recommended.Yes
Nodal Officer RecommendedAs per file attached
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
UttarakhandState SecretaryRecommended20/09/2016 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
DehradunState Government1(312)/201616/09/2016
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/UK/ROAD/20227/2016ROAD2022720166316,601,492.006,601,492.002021-03-30SBIN308818511110Union Bank Of IndiaNEFT/RTGS (Challan)2021-03-202021-03-22
FP/UK/ROAD/20227/2016ROAD202272016142933,203.00933,203.002024-02-026016020240202411579Union Bank Of IndiaUnion Bank Of India (Challan)2023-12-232024-01-11
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 5.36   (iii). No. of Maintenance years: 7   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)5.36
  Status of CA Land so identified : Non Forest Area   Site Name : Kapkot   Location Details : Goushi   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
North KumaunBageshwarKapkot6707 Dec 20165.36
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/UK/ROAD/20227/201603 Mar 2022No DataAs per file attached
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/UK/ROAD/20227/201622 Oct 2024
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/UK/ROAD/20227/2016IN-PRINCIPLENo Data