PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : TN-061/2020
1. Location of the project/Scheme : Tamil Nadu
 (i) State / Union Territory : Tamil Nadu  (ii) District : Coimbatore  (iii) Forest Division : Coimbatore  (iv) Area of forest land proposed for diversion (in ha.) : 0.62  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Coimbatore0.62Section 26
Total 0.62
Division 1. : Coimbatore
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Coimbatore0.62
Total0.62
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.620.25Eco 3
Total. 0.62


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Prosophis Juliflora000000
Total 0 00 00 0
Sub Total (No of Trees.) 0


5. Working plan prescription for the forest land proposed for diversion : No data
6. Brief note on vulnerability of the forest area to erosion : There is no possibility of land slid occur
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Elephant, Wild boar, Spotted deer
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : NIL
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 7.55
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
111.24PFCoimbatore499/3    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Topo sketch on S.I Sheet - CA Land 1.24
2 Land suitability certificate of the DFO
3 Geo reference map for the CA land
4 CA Scheme
5 letter of the User Agency regarding 1.24 Ha.

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Coimbatore470244.20109073.04102.1457352366.1630/09/202026.3668.74
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
CoimbatoreCoimbatoreDFOYesOne02/12/2020
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
CoimbatoreCoimbatoreDFO Recommended1. I inspected the site on 02.12.2020 and found that the proposed non linear area of 0.62 Ha for Creation of Christian Burial Ground falls within Madukkarai Forest Block – V Reserved land. 2. The proposed area for diversion does not have any archeological and heritage related monuments. 3. There is no Tribal Right affected by this project. 4. Flagship species like tiger is not available in this Reserved Land. Hence there is no threat to major wildlife species. 5. This project in Madukkarai Forest Block – V Reserved land has minimum effects on environment. Hence I recommend that an area of 0.62 Ha. of Forest land in the Madukkarai Forest Block – V Reserved land in Madukkarai Range of Coimbatore Forest Division may be diverted for Creation of Christian Burial Ground.
CoimbatoreCF RecommendedNo alternative non forest land is available for this project. The proposal is for public oriented purposes. It is not likely to adversely impact on forest and wildlife.Yes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Tamil NaduState SecretaryRecommended08/02/2021 Recommended State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ChennaiRegional Office4-TNB070/2021-CHN30/11/2021
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/TN/Others/57952/2020Approved In-PrincipleNo Data