PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
RJ-024/2015
1.
Location of the project/Scheme :
Rajasthan
(i)
State / Union Territory :
Rajasthan
(ii)
District :
Baran
(iii)
Forest Division :
Baran Territorial
 (iv)
Area of forest land proposed for diversion (in ha.) :
1.14
 (v)
Category of the Proposal:
Road
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Baran Territorial
1.14
Protected Forest
Total
1.14
Division 1. : Baran Territorial
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Baran
1.14
Total
1.14
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
1.14
0
Eco 3
Total.
1.14
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
NIL
5.
Working plan prescription for the forest land proposed for diversion :
protection overlapping working circle
6.
Brief note on vulnerability of the forest area to erosion :
less
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Nilgai
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
Yes
(a)Details of violation(s):
NO FIR
(b) Period of Work done(year) :
2015
(c) Area of forest land involved in violation (in ha.) :
1.14
S. No.
Name of person responsible for violation
Designation & Address of person responsible for violation
Action taken against the person responsible for violation
1
AK Gupta HOD
Retired
NO
2
Sunil Mathur SE
Retired
NO
3
HP Meena Exen
Executive Engineer PWD Sury and qualify Control office Baran
NO
4
Basant Kumar Aen
Aen pwd office Kelwada
NO
12.
Whether work in violation is still in progres(Yes/No) :
No
13.
Details of compensatory afforestation scheme
(i).
Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no
District Name
Village
Area(in ha.)
khasra
KML file
Present Owner file
1
Baran
bilandi
1.14
138
(ii).
Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iii).
Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A:
(iv).
Copy of CA scheme details:
(iv).
Copy of CA scheme details:
NA
Additional information Details
S. No.
Documents
Remarks
1
npv
2
Land suitability
3
CA Scheme
4
site ins Report
5
factual report
6
gajat notifision report
7
TOPO SHEET for CA land
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Baran
699600
224884.33
1286.302
32
234.412
25/06/2020
131069
00
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Baran Territorial
Kota
DFO
Yes
One
14/02/2015
Kota
CF
No
No Data
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Baran Territorial
Kota
DFO
Recommended
1.There is no alternative way other than passing through the proposed forest area. 2.To provide people with basic infrastructure in the form of good road so as to improve their living standard.
Kota
CF
Recommended
quetiapin ritalin
markenavntablet.site
quetiapin wirkstoff
Yes
Nodal Officer
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Rajasthan
State Secretary
Recommended
11/03/2015
Recommended
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Jaipur
Regional Office
8B/Raj/06/24/2015
19/01/2021
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/RJ/ROAD/7127/2014
ROAD71272014441
2933555
2024-05-19
2024-05-29
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/RJ/ROAD/7127/2014
Approved In-Principle
No Data
Print
Checklist for State Nodal Officer
×