PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : KL-066/2017
1. Location of the project/Scheme : Kerala
 (i) State / Union Territory : Kerala  (ii) District : Thrissur  (iii) Forest Division : Peechi Wildlife Sanctuary,Thrissur  (iv) Area of forest land proposed for diversion (in ha.) : 0.244  (v)

Category of the Proposal: Transmission Line
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Peechi Wildlife Sanctuary0.098Reserved Forest
2Thrissur0.146Reserved Forest
Total 0.244
Division 1. : Peechi Wildlife Sanctuary
3. District wise area to be diverted in the division
S. No. DistrictArea(in ha.)
NIL
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.0980.5Eco 1
Total. 0.098


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Terminalia PaniculataMaruthu000000
Total 0 00 00 0
Sub Total (No of Trees.) 0


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : No tree felling required hence susceptibility to soil erosion is nill
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Already Diverted Area for NH 544,No wildlife present
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : The Proposed Under Ground Power Cable in passing through the land already bee diverted to NH. The proposed cable is laying along side of the existing NH 544. This land id devoid of any vegetation hence no tree felling is required. More over the proposed cable is laying only 2 metre below ground level for a length of 490 metre with a width of 2 metre, covering an area of only 0.098 Ha. hence it is reported that there would not be any impact upon animals to the proposed project. so the impact is nil or barest minimum.
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): Yes
  Details of Protected Area and comments on the impact of Project on the ESZ : Since the power line is passing through already diverted area and is also an under ground cable there is no adverse impact on ESZ
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 0
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.098Peechi-Vazhani Wildlife SanctuaryPeechiParavattani Mala Under Vellani Section    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
NIL
Division 2. : Thrissur
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Thrissur0.146
Total0.146
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.1460Eco 1
Total. 0.146


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL
5. Working plan prescription for the forest land proposed for diversion : Protection of forest land is only proposed
6. Brief note on vulnerability of the forest area to erosion : The proposed area is not/least vulner
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Nil
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : Yes
  Details and comments on the impact of Project on such areas : Least vulnerable
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
NO Data
(ii). Copy of CA scheme details: NA (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.: (V). Copy of NOC from Competent Authority:
Additional information Details
S. No. DocumentsRemarks
NIL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Thrissur30320029805.7549.1625698.617/08/20170698.60
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Peechi Wildlife SanctuaryPalakkad Field Director Parambikulam Tiger ReseveDFOYesTwo07/08/2017,12/08/2017
ThrissurCentral circle, ThrissurDFOYesOne12/08/2017
 Palakkad Field Director Parambikulam Tiger ReseveCFYesOne31/08/2017
 Central circle, ThrissurCFYesOne07/10/2017
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Peechi Wildlife SanctuaryPalakkad Field Director Parambikulam Tiger ReseveDFO RecommendedDFO
ThrissurCentral circle, ThrissurDFO RecommendedThe forest land as proposed by the User agency is unavoidable and is the barest minimum for the scheme.
Palakkad Field Director Parambikulam Tiger ReseveCF RecommendedThe requirement of Forest Land as proposed by the user agency is unavoidable and is the barest minimum for the project.Yes
Central circle, ThrissurCF RecommendedLaying of 320 KV HVDC underground cable from Wadakkenchery to Thrissur in the utility corridor of NH 544. Yes
Nodal Officer Recommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
KeralaState SecretaryRecommended07/04/2018 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
BangaloreRegional OfficeNo.4-KLB1153/2018-BAN09/10/2018
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/KL/TRANS/27023/2017TRANS2702320178876633486633482019-04-29SBIN319119540126Corporation BankNEFT/RTGS (Challan)2019-02-262019-04-13
FP/KL/TRANS/27023/2017TRANS270232017887663348400000002019-08-22SBINR52019082200113663Corporation BankNEFT/RTGS (Challan)NANA
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/KL/TRANS/27023/201714 May 2019No DataCA land is not required as the extent of forest land needed is less than one ha.
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/KL/TRANS/27023/201714 May 2019
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/KL/TRANS/27023/201706 Jul 2019
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/KL/TRANS/27023/201724 Sep 2019APPROVED