PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : KL-038/2022
1. Location of the project/Scheme : Kerala
 (i) State / Union Territory : Kerala  (ii) District : Palakkad  (iii) Forest Division : Nemmara  (iv) Area of forest land proposed for diversion (in ha.) : 0.7922  (v)

Category of the Proposal: Transmission Line
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Nemmara0.7922Cheramangalam Vested Forest (VFC 199/1 Andazhi-Edamalakunnu Malavaram Bit-I)
Total 0.7922
Division 1. : Nemmara
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Palakkad0.7922
Total0.7922
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.792250Eco 1
Total. 0.7922


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Syzigium CuminiNjaval1205200
2Gmelina ArboreaKumizh057300
3Bauhinia ParvifloraMandharam010100
4Misc. SpeciesManjapavatta250000
5Azadirachta IndicaAryaveppu181000
6Emblica OfficinalisNelli023000
7Tectona GrandisTeak064000
8Misc. SpeciesManimaruthu031000
9Misc. SpeciesKudakappala110000
10Grewia TiliaefoliaChadachi001000
11SappanPathimugham010000
12Alstonia ScholarisPala100000
13Terminalia PaniculataMaruthu030000
14Misc. SpeciesAnnakkara010000
15Albezzia LabbeckVaka001000
16Misc. SpeciesKarivaka000001
17Ficus benghalensisAal010000
18Borasis FlebiliferKarimbana100000
19Holoptelia integrifoliaAval010000
20Misc. SpeciesOduku001100
21Misc. SpeciesKanjiram001000
22Misc. SpeciesVelleetti000100
23Terminalia ArjunaNeermaruthu020000
24Misc. SpeciesMullan Kazhanji233110
Total 9 6328 91 1
Sub Total (No of Trees.) 111


5. Working plan prescription for the forest land proposed for diversion : Not Applicable
6. Brief note on vulnerability of the forest area to erosion : Proposed area is covered with the moist decidous forests with 50 percentage of vegetation
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Peacock,Other Reptiles and Mammals
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
NO Data
(ii). Copy of CA scheme details: NA (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.: (V). Copy of NOC from Competent Authority:
Additional information Details
S. No. DocumentsRemarks
1 CA land is not required due to the required forest land for diversion is less thaan 1 Ha.

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Palakkad4480001599087.7303432.99610/11/2022035.378
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
NemmaraEastern CircleDFOYesOne09/11/2022
 Eastern CircleCFYesOne30/11/2022
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
NemmaraEastern CircleDFO RecommendedRecommended the proposal for diverting 0.7922 Ha of Vested Forest area under Vadakkanchery Section of Alathur Range in Nemmara Division
Eastern CircleCF RecommendedA proposal has been received by this office from Kerala State Electricity Board, Thiruvananthapuram user agency through Divisional Forest Officer, Nemmara for diversion of forest land under Forest Conservation Act, 1980 for the purpose of “Upgradation of existing 12.5 Km of 66 KV SC line to 110 KV DC line from Kalappatty to Nemmara” for an area of 0.7922 Ha. The proposed forest land is for the purpose of “Upgradation of existing 12.5 Km of 66 KV SC line to 110 KV DC line from Kalappatty to Nemmara” and the land proposed by the user agency is barest minimum and there is no other suitable alternatives the proposal is recommended for forest clearance as per the norms of MoEF& CC, Government of India.Yes
Nodal Officer RecommendedThe requirement of forest land proposed by the User Agency is the barest minimum and there is no other suitable alternatives.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
KeralaState SecretaryRecommended24/02/2023Proposal recommended for Stage I clearanceState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
BangaloreRegional OfficeF.No.4-KLB1438/2023-BAN15/03/2023
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/KL/TRANS/155551/2022TRANS1555512022653126418512641852023-03-30916468Union Bank Of IndiaNEFT/RTGS (Challan)2023-03-212023-03-22
FP/KL/TRANS/155551/2022TRANS1555512022900201500020150002023-09-16164884Union Bank Of IndiaNEFT/RTGS (Challan)2023-08-172023-08-17
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/KL/TRANS/155551/202203 Apr 2023No DataThe land required by User Agency for diversion is less than 1 hectare, hence CA land is not mandatory.
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/KL/TRANS/155551/202203 Apr 2023
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/KL/TRANS/155551/2022The proposal may be considered and onward submission to Government of India for stage II clearance at the earliest.13 Apr 2023
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/KL/TRANS/155551/202227 Mar 2024APPROVED