PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : JK-059/2021
1. Location of the project/Scheme : Jammu and Kashmir
 (i) State / Union Territory : Jammu and Kashmir  (ii) District : Doda  (iii) Forest Division : Bhaderwah Forest Division  (iv) Area of forest land proposed for diversion (in ha.) : 0.3533  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Bhaderwah Forest Division0.3533Reserved Forest
Total 0.3533
Division 1. : Bhaderwah Forest Division
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Doda0.3533
Total0.3533
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.35330Eco 5
Total. 0.3533


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL
5. Working plan prescription for the forest land proposed for diversion : Reboisment Working Circle
6. Brief note on vulnerability of the forest area to erosion : No Possibility of erosion during and after constrction of proposed project
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : No
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 91231
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.78RFKellar1/M    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Approval of CA by CCF Jammu
2 Undertaking For Payment Of NPV
3 FOREST AREA PROPOSED FOR DIVERSION
4 LOCATION MAP
5 No Violation (DFO)
6 Statement Showing Detail of Non-Forest Area
7 Certificate of Minimum use of Forest Land
8 Muck Disposal Plan
9 Undertaking For Payment of Cost of Compensatory Afforestation
10 Density of Forest is 0
11 JOINT INSEPCTION REPORT
12 SITE INSPECTION Report
13 Land Suitability
14 Specific rccommendation
15 Undertaking For Payment of Additional Net Present value
16 Main Application Form PART-II
17 Calculation Sheet of Net Present Value

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Doda2625146469.72 408.73101331816/06/2021220 0
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Bhaderwah Forest DivisionChenab Circle DodaDFOYesOne12/06/2021
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Bhaderwah Forest DivisionChenab Circle DodaDFO RecommendedDiversion of 0.3533 ha of forest land for Temporary establishment of Crusher plant for the construction of Uni Directional Khellani Tunnel at village Khellani Tehsil Doda in Bhadarwah Forest Division, is recommended for Forest clearance under Section 2 of Forest Conservation Act, 1980, with the condition to take all necessary steps to ensure that there is no damage in the adjoining areas
Chenab Circle DodaCF RecommendedForest land divertion under APCO infratech pvt limited for temporary establishment of crusher plant for construction of uni directional khellani tunnel is hereby recommended for approval under FCA. Total of 0.3533 hac of forest land near khellani of bhaderwah forest division is recommended. Yes
Nodal Officer Recommendedto construct the Khellani Tunnel
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Jammu and KashmirState SecretaryRecommended06/10/2021Recommended for grant of Stage I approval.State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
JammuRegional Office9-JKA-080/2021-Jammu17/12/2021
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/JK/Others/142143/2021OTHERS1421432021463323,349.00100,000.0028/12/2021PUNBH21362551579Union Bank Of IndiaNEFT/RTGS (Challan)24/12/202127/12/2021
FP/JK/Others/142143/2021OTHERS1421432021463323,349.0023,349.0028/12/2021PUNBH21362550727Union Bank Of IndiaNEFT/RTGS (Challan)24/12/202127/12/2021
FP/JK/Others/142143/2021OTHERS1421432021463323,349.00100,000.0028/12/2021PUNBH21362552826Union Bank Of IndiaNEFT/RTGS (Challan)24/12/202127/12/2021
FP/JK/Others/142143/2021OTHERS1421432021463323,349.00100,000.0028/12/2021PUNBH21362552139Union Bank Of IndiaNEFT/RTGS (Challan)24/12/202127/12/2021
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 0.78   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)0.78
  Status of CA Land so identified : Forest Area   Site Name : Muradabad village   Location Details : Muradabad village   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
1/MarmatRF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/JK/Others/142143/202104 Mar 2022No Datathe detail of CA site is as per approval
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/JK/Others/142143/202105 Mar 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/JK/Others/142143/2021Recommended for Stage-II07 Jul 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/JK/Others/142143/202128 Jul 2022APPROVED