PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : HR-0241/2022
1. Location of the project/Scheme : Haryana
 (i) State / Union Territory : Haryana  (ii) District : Panipat  (iii) Forest Division : Panipat  (iv) Area of forest land proposed for diversion (in ha.) : 0.0197  (v)

Category of the Proposal: Approach Access
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Panipat0.0197Protected Forest
Total 0.0197
Division 1. : Panipat
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Panipat0.0197
Total0.0197
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.01970Eco 3
Total. 0.0197


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1OthersMisc000000
Total 0 00 00 0
Sub Total (No of Trees.) 0


5. Working plan prescription for the forest land proposed for diversion : Na
6. Brief note on vulnerability of the forest area to erosion : No
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : No
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 47611
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.10H43Q15PanipatNohra Drain    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 CA Location Map
2 Checklist
3 Forwording
4 NPV Sheet
5 Other Undertaking
6 Part 2
7 Proposed site map and layout plan
8 Add Charges and Payment Detail
9 Site Inspection
10 CA Site Toposheet
11 CA Scheme
12 EDS Reply with PWD NOC and other
13 EDS Reply Dated 09-05-2024

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Panipat130437.24343.87749.65205409.2531/03/2023128.2120.56
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
PanipatCentral Circle RohtakDFOYesOne18/10/2023
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
PanipatCentral Circle RohtakDFO RecommendedUA has not violated the provisions of FCA, 1980 and no work has been started without proper sanction. UA will pay for C.A. The facilities are essential for the public. Hence, the proposal is recommended.
Central Circle RohtakCF RecommendedUA has not violated the provisions of FCA, 1980 and no work has been started without proper sanction. UA will pay for C.A. The facilities are essential for the public. Hence, the proposal is recommended.Yes
Nodal Officer RecommendedStage I attached
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
HaryanaState SecretaryRecommended29/10/2024Stage I granted State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ChandigarhState GovernmentFCA/96609/09/2024
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/HR/Approach/154224/2022APPROACH154224202244186,479.002024-11-08
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/HR/Approach/154224/2022IN-PRINCIPLENo Data