PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : DN-027/2017
1. Location of the project/Scheme : Dadar & Nagar Haveli
 (i) State / Union Territory : Dadar & Nagar Haveli  (ii) District : Dadra and Nagar Haveli  (iii) Forest Division : Territorial Division  (iv) Area of forest land proposed for diversion (in ha.) : 0.91  (v)

Category of the Proposal: Village Electricity
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Territorial Division0.91Reserved Forest
Total 0.91
Division 1. : Territorial Division
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Dadra and Nagar Haveli0.91
Total0.91
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.910.2Eco 3
Total. 0.91


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Peltoform PterocarpumGulmohar0000221
2Acacia AuricuiformisBangali Baval0000100
3Dalbergia LatifoliaSisu0000010
4Terminalia TomentosaSadad0013300
5OthersKukarval (Dillenia indica)1000000
6Lagerstroemia ParvifloraBondari0020000
7Madhuca indicaMohdo0001010
Total 1 34 64 1
Sub Total (No of Trees.) 19


5. Working plan prescription for the forest land proposed for diversion : Nil
6. Brief note on vulnerability of the forest area to erosion : Nil
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Nil
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 10.65
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
111.82GalondaNorthern Range351    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
NIL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Dadra and Nagar Haveli4910020358230.362500.617/10/201700
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Territorial DivisionForest Department, Dadra & Nagar Haveli, Silvassa.DFOYesOne02/02/2018
 Forest Department, Dadra & Nagar Haveli, Silvassa.CFNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Territorial DivisionForest Department, Dadra & Nagar Haveli, Silvassa.DFO RecommendedThe Diversion of the proposed land is unavoidable and barest minimum. Hence, diversion of 0.91 Ha. of Reserved Forest is hereby recommended
Forest Department, Dadra & Nagar Haveli, Silvassa.CF RecommendedThe proposal is to provide electricity to the Tribal Villages of Sindoni and Loharmal and the land required is the barest minimum and unavoidable.Yes
Nodal Officer Recommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Dadar & Nagar HaveliState SecretaryRecommended26/07/2018 Recommended and approved. State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
GandhinagarState GovernmentDN-027/201726/07/2018
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/DN/VELEC/30058/2017VELEC3005820176391,919,605.001,919,605.002018-10-30BKDNR52018103000011951Corporation BankNEFT/RTGS (Challan)2018-09-042018-09-04
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/DN/VELEC/30058/201729 Aug 2023No Dataplantation will be carriedout on double degraded forest land
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/DN/VELEC/30058/201725 Jun 2024
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/DN/VELEC/30058/2017for approval please09 Aug 2024FP/DN/VELEC/30058/2017for approval please09 Aug 2024
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/DN/VELEC/30058/201708 Aug 2024APPROVED