PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
WB-01/2014
1.
Location of the project/Scheme :
West Bengal
(i)
State / Union Territory :
West Bengal
(ii)
District :
Burdwan
(iii)
Forest Division :
Burdwan,Durgapur
 (iv)
Area of forest land proposed for diversion (in ha.) :
18.4321
 (v)
Category of the Proposal:
Others
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Burdwan
9.31
Protected Forest
2
Durgapur
4.22
Protected Forest
Total
13.53
Division 1. : Burdwan
3.
District wise area to be diverted in the division
S. No.
District
Area(in ha.)
NIL
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
9.31
0.4
Eco 3
Total.
9.31
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
NIL
5.
Working plan prescription for the forest land proposed for diversion :
As per working plan prescription for the period fr
6.
Brief note on vulnerability of the forest area to erosion :
Forest floor will not be altered/damaged/eroded in
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.5
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Python, Wolf, Wild Boar, Wild Fowls, Gosap.
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
Yes
(vi).
Details and comments on the impact of Project on such species of Flora and Fauna:
Flora
S.No.
Species
Species Local Name
1
Flora
Simul
2
Fauna
Python
3
Flora
Mahul
4
Flora
Asan
5
Flora
Pial
6
Flora
Rahara
7
Flora
Gulancha
8
Flora
Lata Palash
9
Flora
Satamuli Creeper
10
Fauna
wolf
11
Fauna
wild boar
12
Fauna
wild fowls
13
Fauna
gosap
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
No
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
9.22
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
9.31
Bankura PF
Indpur
Indpur
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
NIL
Division 2. : Durgapur
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Burdwan
13.53
Total
13.53
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
4.22
0.4
Eco 3
Total.
4.22
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
NIL
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
Forest floor will not be altered/damaged/eroded in
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.1
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Python, wild boar, wolf, wild fowls, monitor lizard etc
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
4.18
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
4.22
Bankura PF
Indpur
Indpur
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
NIL
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Burdwan
702400
25385
127.48
6
26.46
127.48
26.46
102.002
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Burdwan
South- East Circle
DFO
Yes
One
12/02/2015
Durgapur
South- East Circle
DFO
Yes
One
09/05/2015
South- East Circle
CF
Yes
One
19/06/2015
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Burdwan
South- East Circle
DFO
Recommended
There is hardly any scope for laying pipelines and access road to well pad through private land and accordingly the user agency has no alternative but to apply for diversion of Forest Land for their project activities and the forest land 9.32 ha proposed for diversion for such project finally is justified.
No Data
Durgapur
South- East Circle
DFO
Recommended
There is hardly any scope for laying pipelines and access road to well pad through private land and accordingly the user agency has no alternative but to apply for diversion of Forest Land for their project activities and the forest land 4.22 ha proposed for diversion for such project finally is justified.
No Data
South- East Circle
CF
Recommended
Diversion of 4.75 ha forest land for this project for digging of CBM well has been already approved by MOEFCC Govt of India. In current proposal for connecting of well sites and for taking gas out, pipeline is required and for carriage of machine and material, road is justified
quetiapin ritalin
markenavntablet.site
quetiapin wirkstoff
Yes
Nodal Officer
Recommended
Keeping in view the importance of alternate energy
quetiapin ritalin
markenavntablet.site
quetiapin wirkstoff
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
West Bengal
State Secretary
Recommended
04/08/2015
Recommended
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Kolkata
Regional Office
5-WBC087/2014-BHU
02/02/2016
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/WB/Others/7248/2014
OTHERS72482014845
12,276,620.00
AXISF17062062055
Corporation Bank
NEFT/RTGS (Challan)
2017-03-03
2017-03-03
FP/WB/Others/7248/2014
OTHERS72482014897
100,000.00
100,000.00
2017-11-14
SBIN417317764830
Corporation Bank
NEFT/RTGS (Challan)
2017-11-07
2017-11-07
FP/WB/Others/7248/2014
OTHERS72482014897
100,000.00
100,000.00
2017-11-14
SBIN417317764830
Corporation Bank
NEFT/RTGS (Challan)
NA
NA
FP/WB/Others/7248/2014
OTHERS72482014897
100,000.00
100,000.00
2017-11-14
SBIN417317764830
Corporation Bank
NEFT/RTGS (Challan)
NA
NA
FP/WB/Others/7248/2014
OTHERS72482014897
100,000.00
100,000.00
2017-11-14
SBIN417317764830
Corporation Bank
NEFT/RTGS (Challan)
NA
NA
FP/WB/Others/7248/2014
OTHERS72482014836
10,083,403.40
10,083,403.40
2023-10-10
198199
Union Bank Of India
NEFT/RTGS (Challan)
2023-08-03
2023-08-04
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
13.54
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
13.54
Status of CA Land so identified :
Non Forest Area
Site Name :
Muktudihi Village
Location Details :
JL No 118, LR Plot No 364.365.407. 425
Uploaded GPS File :
Uploaded Scanned copy of Map :
Mutation Status :
Mutated
Mutation Status
Circle Name.
Name of Division.
Name of Range.
Mutation Order No.
Mutation Date
How Much Area of Mutated Land Received
Mutation Letter
Central
Bankura (South)
Indpur
4286-GE(M)/3M-96/12 pt-IV dated 26.09.22
06 Feb 2023
13.54
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/WB/Others/7248/2014
23 Feb 2023
No Data
verified
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/WB/Others/7248/2014
21 Nov 2023
Compliance Details Submitted by User Agency(old)
Proposal No.
Compliance Details submitted on(Date)
Reject Remarks
Reject Date
Uploaded Letter
FP/WB/Others/7248/2014
02 Nov 2023
EDS: until and unless portal shows status of payment as paid further process is not possible
06 Nov 2023
FP/WB/Others/7248/2014
23 Feb 2023
EDS: Pl address EDS
14 Jul 2023
FP/WB/Others/7248/2014
26 Oct 2023
EDS: please follow up with bank to get payment cleared
30 Oct 2023
FP/WB/Others/7248/2014
30 Oct 2023
EDS: please follow up with bank to get payment cleared
31 Oct 2023
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/WB/Others/7248/2014
may pl be forwarded to IRO Kolkata
24 May 2023
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/WB/Others/7248/2014
01 Jan 2024
APPROVED
Print
Checklist for State Nodal Officer
×