PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : UP-091/2017
1. Location of the project/Scheme : Uttar Pradesh
 (i) State / Union Territory : Uttar Pradesh  (ii) District : Mirzapur  (iii) Forest Division : Forest Division Mirzapur  (iv) Area of forest land proposed for diversion (in ha.) : 6.5475  (v)

Category of the Proposal: Transmission Line
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Forest Division Mirzapur6.5475Reserved Forest
Total 6.5475
Division 1. : Forest Division Mirzapur
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Mirzapur6.5475
Total6.5475
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
16.54750.01Eco 3
Total. 6.5475


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Madhuca indicaMahua 020000
Total 0 20 00 0
Sub Total (No of Trees.) 2


5. Working plan prescription for the forest land proposed for diversion : That forest Land should be diverted for non forestry purpose under FCA 1980
6. Brief note on vulnerability of the forest area to erosion : The forest land is not vulnerable for soil erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Nil
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 18.39746
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1114.00RFLalganjVijaypur K.N.3    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 10 km distance senturi certificate
2 ca bachanbaddhta certificate
3 ca shutibilty ceritificate
4 fra certificate
5 gujut notification section 20
6 lease awadhi certificate
7 manak sharte
8 no other land avlable cerificate
9 part 2
10 reclamanation plan
11 vittiy prasashnik swikriti
12 cast and benifite analysis
13 land schdule
14 gair van bhumi ki sahmati
15 joint inspection
16 npv calculation
17 project description
18 van swaroop
19 efected tres
20 benifisory village family certificate
21 chequ list
22 npv ceritificate
23 power of atorny
24 CA
25 ACA
26 Tree To feld

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Mirzapur452200.00104405.00348.168445176.25405/06/2017176.254190.046
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
 Mirzapur Circle MirzapurCFNoNo Data
 Nodal OfficerNoNo Data
Forest Division MirzapurMirzapur Circle MirzapurDFOYesOne24/05/2017
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Forest Division MirzapurMirzapur Circle MirzapurDFO RecommendedProject Recommended as above
Mirzapur Circle MirzapurCF RecommendedRecommended
quetiapin ritalin quetiapin mod angst quetiapin wirkstoff
Yes
Nodal Officer RecommendedRecommended for approval
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Uttar PradeshState SecretaryRecommended02/08/2017 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
LucknowRegional Office8B/UP/04/50/201701/01/2018
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/UP/TRANS/24154/2017TRANS2415420173566,984,518.006,984,518.0025/01/2018SBINR52018012500010959Corporation BankNEFT/RTGS (Challan)03/01/201804/01/2018
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/UP/TRANS/24154/2017Approved In-PrincipleNo Data