PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : UP-039/2019
1. Location of the project/Scheme : Uttar Pradesh
 (i) State / Union Territory : Uttar Pradesh  (ii) District : Muzaffarnagar  (iii) Forest Division : Social Forestry Division Muzaffarnagar  (iv) Area of forest land proposed for diversion (in ha.) : 31.5323  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Social Forestry Division Muzaffarnagar31.5323Protected Forest
Total 31.5323
Division 1. : Social Forestry Division Muzaffarnagar
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Muzaffarnagar31.5323
Total31.5323
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
131.53230.5Eco 3
Total. 31.5323


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Mangifera IndicaAam31242291532
2Terminalia ArjunaArjun132197181164351
3Saraca AsocaAshok3266111
4Psidium GuajavaAmood002000
5BaheraBahera058730
6Melia AzadirachtaBakain626231262
7Aegle MarmelosBel11810100
8EucalyptusEucalyptus81806148939831246
9Ficus RacemosaGullar000100
10Delonix RegiaGulmohar002001
11Syzigium CuminiJamun115106229234135241
12Artocarpus HeterophyllusKathal000001
13Azadirachta IndicaNeem11317182013
14Ficus ReligiosaPeepal3887310
15Populus sppPoplar093302
16Bombax CeibaSemal004102
17Dalburgia SisooShisham2038305163108
18Albezzia LabbeckSirus122910943
19OthersBer0511972
20OthersChir000101
21OthersCut Sagaun44281121
22OthersDaya0125101
23OthersJangli Jalebbi173728
24OthersKanji267351443321
25Otherskarala001010
26OthersKhadal Badal011100
27OthersKhajur011410
28OthersKikar101442
29OthersKumhar14173210
30OthersKunti010100
31OthersLisotha063421
32OthersPhulbari000001
33OthersPapri5175342
34OthersPilkhan001000
35OthersRenta155110
36OthersSalbadal001000
37OthersSagund1030000
38OthersSapeda100000
39OthersShehtoot353331
40OthersTun16107120
41OthersTunti1310000
Total 268 6991225 15451460 2054
Sub Total (No of Trees.) 7251


5. Working plan prescription for the forest land proposed for diversion : As per Plantation working circle of working plan
6. Brief note on vulnerability of the forest area to erosion : No Vulnerability for erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : No Wildlife present in and around the forest land proposed for diversion
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 211.03846
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1134Hanuwa Forest Block Raipur ChitrakootNA    View file
2230Deshah Forest BlockBargarhNA    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Duly signed Joint Tree Survey Report
2 Sudh NPV duly signed by DFO
3 Cost benefit Analysis duly signed by DFO
4 Linear Plan of Forest Land duly signed by DFO
5 FRA certificate
6 Beneficiary Villages
7 Environment Clearance
8 DFO site Inspection Report
9 Project site picture during Site visit by DFO
10 Tree List and Summary
11 Van Swaroop
12 Forest Area sheet duly signed by DFO
13 NPV Calculation
14 TCS duly signed by DFO
15 Muck disposal Plan duly signed by DFO
16 Task Force
17 Land Suitability
18 Wildlife and ECO Sensitive Zone Certificate

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Muzaffarnagar4008006199121.929836339.6714/04/2019339.6717.50
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Social Forestry Division MuzaffarnagarSaharanpur Circle SaharanpurDFOYesOne26/07/2019
 Saharanpur Circle SaharanpurCFNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Social Forestry Division MuzaffarnagarSaharanpur Circle SaharanpurDFO RecommendedThe requirement of forest land as Proposed by User Agency is unavoidable and bare minimum forest land is 31.5323 ha.
Saharanpur Circle SaharanpurCF RecommendedyesYes
Nodal Officer RecommendedRecommended for approval.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Uttar PradeshState SecretaryRecommended30/09/2019 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
LucknowRegional Office8B/UP/06/84/2019/FC30/01/2020
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/UP/ROAD/37341/2018ROAD37341201895346,424,283.0046,424,283.0011/02/2020P20021129537628Corporation BankNEFT/RTGS (Challan)05/02/202007/02/2020
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 64   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 2
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)34
  Status of CA Land so identified : Forest Area   Site Name : Hanuwa Forest Block   Location Details : Hanuwa Forest Block in Repura Range Chitrakot Division   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Hanuwa Forest BlockRF
  No. of patches : 2
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
2Block(Polygon)30
  Status of CA Land so identified : Forest Area   Site Name : Deshah Forest Block   Location Details : Deshah Forest Block in Repura Range Chitrakot Division   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Deshah Forest BlockRF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/UP/ROAD/37341/201816 Mar 2020No DataApproved.
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/UP/ROAD/37341/201812 Jan 2021
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/UP/ROAD/37341/201821 Jan 2021
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/UP/ROAD/37341/201811 Feb 2021APPROVED