PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : UP-02/2018
1. Location of the project/Scheme : Uttar Pradesh
 (i) State / Union Territory : Uttar Pradesh  (ii) District : Gorakhpur  (iii) Forest Division : Forest Division Gorakhpur  (iv) Area of forest land proposed for diversion (in ha.) : 4.225  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Forest Division Gorakhpur4.225Protected Forest
Total 4.225
Division 1. : Forest Division Gorakhpur
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Gorakhpur4.225
Total4.225
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
14.2250.4Eco 3
Total. 4.225


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Ficus ReligiosaPipal264700
2Dalburgia SisooShisham022000
3Albezzia LabbeckSiras500000
4Azadirachta IndicaNeem18224100
5Anthocephalus CadambaKadam6100000
6Nyctanthes Arbor-TristisHarsingar210000
7Delonix RegiaGold Mohar442000
8Tectona GrandisSagaun024000
9Castanopsis TribuloidesKanail900000
10EucalyptusUkeliptus020000
11Cassia FistulaAmaltas400000
12Melia AzadirachtaBakain240000
13Saraca AsocaAshok310000
14Moringa oleiferaSahjan630000
15Aegle MarmelosBel410000
16Morus LaevigataSahtut310000
17Psidium GuajavaAmrud1700000
18Emblica OfficianalisAmla700000
19Tabubia RoseaKukath440000
20Ficus BengalensisBargad110100
21Ficus TomentosaGular120000
22Mangifera IndicaAam710100
23Acacia NiloticaBabul020000
24Bombax CeibaSemal000100
25Prosophis JulifloraPraspis500000
26Ficus LacorPakad311000
27Terminalia ArjunaArjun110000
28Syzigium CuminiJamun210000
29Tamarindus IndicaImali100000
30Terminalia bellericaGutel001000
31Holoptelia integrifoliaChilbil001000
32Artocarpus HirsutaBadahal010000
33Phoebe Attenuata Nees.Khajur240000
Total 119 7719 110 0
Sub Total (No of Trees.) 226


5. Working plan prescription for the forest land proposed for diversion : The area is Covered under plantation working circle of the working Plan.
6. Brief note on vulnerability of the forest area to erosion : The area is not Vulnerable to soil erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : No
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 57.38850
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
118.45OtherSahjanwan0    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Site Inception
2 DM FRA Certificate
3 NPV Calculation
4 DFO. Inception Report
5 Part-2

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Gorakhpur3484005713145.08208.2622/02/20188.26110.15
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Forest Division GorakhpurGorakhpur Circle GorakhpurDFOYesOne19/02/2018
 Nodal OfficerNoNo Data
 Gorakhpur Circle GorakhpurCFNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Forest Division GorakhpurGorakhpur Circle GorakhpurDFO RecommendedProposal is requirement in public interest
Gorakhpur Circle GorakhpurCF RecommendedProposal is requirement in public interestYes
Nodal Officer RecommendedRecommended for Approval
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Uttar PradeshState SecretaryRecommended25/04/2018Recommended for Approval. State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
LucknowRegional Office8B/UP/06/45/2018/FC22/06/2018
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/UP/ROAD/30203/2017ROAD3020320173489,131,525.009,131,525.0016/08/2018RBI2291820588345Corporation BankNEFT/RTGS (Challan)21/07/201824/07/2018
FP/UP/ROAD/30203/2017ROAD3020320173489,131,525.002,097,880.0016/08/2018RBI2291820588354Corporation BankNEFT/RTGS (Challan)NANA
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 8.45   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Strip(Avenue)5
  Status of CA Land so identified : Forest Area   Site Name : Kaalesar to Toll Plaza Road (NH-28) in (Km No:-0.00 to 5,00) Forest Range:- Sahjanwa, District:- Gorakhpur   Location Details : Kaalesar to Toll Plaza Road (NH-28) in (Km No:-0.00 to 5,00) Forest Range:- Sahjanwa, District:- Gorakhpur   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Protected ForestPF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/UP/ROAD/30203/201717 Mar 2026No DataApproved.
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/UP/ROAD/30203/2017Approved In-PrincipleNo Data