PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : UP-056/2021
1. Location of the project/Scheme : Uttar Pradesh
 (i) State / Union Territory : Uttar Pradesh  (ii) District : Lakhimpur Kheri  (iii) Forest Division : Forest Division, North Kheri  (iv) Area of forest land proposed for diversion (in ha.) : 0.04674  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Forest Division, North Kheri0.04674Protected Forest
Total 0.04674
Division 1. : Forest Division, North Kheri
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Lakhimpur Kheri0.04674
Total0.04674
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.046740Eco 4
Total. 0.04674


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL
5. Working plan prescription for the forest land proposed for diversion : In this division there is no Working plan but there is Tiger Conservation Plan in which Road side plantation is prescribed for the forest land proposed for diversion.
6. Brief note on vulnerability of the forest area to erosion : site is not vulnerable to erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : monkey, jackal birds etc
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : Yes
  Details and comments on the impact of Project on such areas : Reserve forest of notified buffer zone is present within 10 km from boundary of forest land prosed for diversion but these forest are are in small small patches surrounded by agricultural land. forest boundaries of Dudhwa National Park and Kishanpur WLS are more than 15 km away so the project will not have much impact
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 3.53
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.10PFSampurna Nagar0    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Georeference map of CA
2 joint survey report
3 CA Estimate
4 FRA certificate

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Lakhimpur Kheri768000165549153.48776819009/03/2021111.39640
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Forest Division, North KheriLucknow Circle LucknowDFOYesOne13/02/2021
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Forest Division, North KheriLucknow Circle LucknowDFO RecommendedSince the requirement of Protected Forest land for Entry/ Exit Approach to Proposed IOCL Retail Outlet on Palia Trikolia Khajuria road SH 101 in Km. 117 Chainage 117.8 at right side of road at Gata No. 193, Village Paidiya,Tehsil Palia, District Lakhimpur Kheri in North Kheri Forest Division Lakhimpur Kheri, is minimum, no tree is to cut and no alternative is available hence the project is recommended for the benefit/interest of local people
Lucknow Circle LucknowCF RecommendedSince the requirement of Protected Forest land for Entry/ Exit Approach to Proposed IOCL Retail Outlet on Palia Trikolia Khajuria road SH 101 in Km. 117 Chainage 117.8 at right side of road at Gata No. 193, Village Paidiya,Tehsil Palia, District Lakhimpur Kheri in North Kheri Forest Division Lakhimpur Kheri, is minimum, no tree is to cut and no alternative is available hence the project is recommended for the benefit/interest of local peopleYes
Nodal Officer RecommendedRecommended for Approval.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Uttar PradeshState SecretaryRecommended20/01/2022 RecommendedState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
LucknowRegional Office8B/UP/06/24/2022/FC10/05/2022
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/UP/Others/49746/2020OTHERS497462020674384,322.34384,322.3404/06/2022HDFC615473193499Union Bank Of IndiaNEFT/RTGS (Challan)31/05/202202/06/2022
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 0.1   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Strip(Avenue)0.1
  Status of CA Land so identified : Forest Area   Site Name : Sampurna Nagar Tatarganj Road, Range-Sampurna Nagar   Location Details : Sampurna Nagar Tatarganj Road, Range-Sampurna Nagar   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Protected ForestPF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/UP/Others/49746/202008 Aug 2025No DataApproved.
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/UP/Others/49746/202008 Aug 2025
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/UP/Others/49746/202013 Aug 2025
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/UP/Others/49746/202022 Aug 2025APPROVED