PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : UP-03/2016
1. Location of the project/Scheme : Uttar Pradesh
 (i) State / Union Territory : Uttar Pradesh  (ii) District : Hathras  (iii) Forest Division : Social Forestry Division Hathras  (iv) Area of forest land proposed for diversion (in ha.) : 0.065378  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Social Forestry Division Hathras0.065378Protected Forest
Total 0.065378
Division 1. : Social Forestry Division Hathras
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Hathras0.065378
Total0.065378
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.0653780.1Eco 3
Total. 0.065378


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Eucalyptus spp000000
Total 0 00 00 0
Sub Total (No of Trees.) 0


5. Working plan prescription for the forest land proposed for diversion : Forest land proposed for diversion is included in the plantation working circle.
6. Brief note on vulnerability of the forest area to erosion : land being plain,is not susceptible to erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : rhesus macaque,squirrels etc
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : Yes
  (a)Details of violation(s): Protected Forest between km.234 of Pilibhet Bharat
   (b) Period of Work done(year) : 5
   (c) Area of forest land involved in violation (in ha.) : 0.065378
S. No. Name of person responsible for violation Designation & Address of person responsible for violationAction taken against the person responsible for violation
1Sanjeev kumar sharmaRepresentative of Essar vill jatoi mursan hathrasconstruction of approach Road by the user agency on 10.11.2017 and the stopping of work by the Forest Department and Issued the H2 Case No 05 Hathras 2022 23 Dated 07. 04.2022 under section 33 of the Indian Forest Act. 1927
12. Whether work in violation is still in progres(Yes/No) : No
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 3.619
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.16PFHathras0    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 NPV calculation
2 MUCK Disposal
3 EDS Report
4 NPV Certificete
5 Penal Afforestation
6 penal NPV calculation
7 Polution Noc

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Hathras1800011615.611144.725443454.853826/07/2022104.6024.25
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Social Forestry Division HathrasAligarh Circle AligarhDFOYesOne05/05/2022
 Aligarh Circle AligarhCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Social Forestry Division HathrasAligarh Circle AligarhDFO RecommendedRecommended
Aligarh Circle AligarhCF RecommendedRecommended in public interest for approval.Yes
Nodal Officer RecommendedRecommended for Approval.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Uttar PradeshState SecretaryRecommended17/04/2023RecommendedState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
LucknowRegional Office8B/UP/06/96/2023/FC17/01/2024
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/UP/Others/16714/2015OTHERS167142015819797,720.00797,720.0013/02/2024CNRBR52024021Union Bank Of IndiaNEFT/RTGS (Challan)08/02/202408/02/2024
FP/UP/Others/16714/2015OTHERS167142015819797,720.00797,720.0013/02/2024CNRBR52024021373710686Union Bank Of IndiaNEFT/RTGS (Challan)NANA
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 0.16   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)0.16
  Status of CA Land so identified : Forest Area   Site Name : FOREST BLOCK:-VARDHWARI, FOREST RANGE:- HATHRAS, FOREST DIVISION:- HATHRAS, DISTRICT HATHRAS   Location Details : FOREST BLOCK:-VARDHWARI, FOREST RANGE:- HATHRAS, FOREST DIVISION:- HATHRAS, DISTRICT HATHRAS   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
FOREST BLOCK:- VARDHWARIRF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/UP/Others/16714/201526 Mar 2024No DataApproved.
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/UP/Others/16714/201513 May 2024
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/UP/Others/16714/201501 May 2024EDS: CF Reply Latter has been not uploaded.01 May 2024
FP/UP/Others/16714/201528 Mar 2024EDS: EDS29 Apr 2024
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/UP/Others/16714/201528 Mar 2024
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/UP/Others/16714/201531 May 2024APPROVED