PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : UK-031/2020
1. Location of the project/Scheme : Uttarakhand
 (i) State / Union Territory : Uttarakhand  (ii) District : Chamoli  (iii) Forest Division : Kedarnath Wild Life Division,Gopeshwar  (iv) Area of forest land proposed for diversion (in ha.) : 1.89  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Kedarnath Wild Life Division,Gopeshwar1.89Village Forest
Total 1.89
Division 1. : Kedarnath Wild Life Division,Gopeshwar
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Chamoli1.89
Total1.89
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
11.890.1Eco 5
Total. 1.89


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Pinus roxburghiiChir021914610
Total 0 219 146 10
Sub Total (No of Trees.) 51


5. Working plan prescription for the forest land proposed for diversion : Area not cover in Working plan
6. Brief note on vulnerability of the forest area to erosion : No erosion porn area
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 1.5
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Leopard, bear wild bore ect
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : NIL
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1ChamoliNauli3.78204, 205, 208
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Additional information Details
S. No. DocumentsRemarks
1 npv
2 land schedule
3 tree list
4 ca cost
5 district profile
6 Bar chart
7 Aeril distance
8 letter sera

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Chamoli803000514793091.986165739.802/03/20204250.96132.71
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Kedarnath Wild Life Division,GopeshwarDirector, Nanda Devi Biosphere Reserve, GopeshwarDFOYesOne25/02/2020
 Director, Nanda Devi Biosphere Reserve, GopeshwarCFYesOne07-03-2020
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Kedarnath Wild Life Division,GopeshwarDirector, Nanda Devi Biosphere Reserve, GopeshwarDFO Recommendedrecommended in public interest
Director, Nanda Devi Biosphere Reserve, GopeshwarCF RecommendedIn Public InterestYes
Nodal Officer RecommendedAs per file attached
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
UttarakhandState SecretaryRecommended06/11/2020 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
DehradunRegional Office8B/UCP/06/138/2020/FC25/02/2021
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/UK/ROAD/43934/2020ROAD4393420203482,516,285.002,516,285.002021-10-05SBIN027745271395Union Bank Of IndiaNEFT/RTGS (Challan)2021-09-232021-09-30
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 3.78   (iii). No. of Maintenance years: 7   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)3.78
  Status of CA Land so identified : Non Forest Area   Site Name : Nauli   Location Details : Nauli   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
Director, Nanda Devi Biosphere Reserve, GopeshwarKedarnath Wild Life Division,GopeshwarNagnath48/26-2(2021-2022)01 Oct 20213.78
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/UK/ROAD/43934/202009 Dec 2021No DataAs per file attched
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/UK/ROAD/43934/202001 Jun 2023EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 25-5-22 to nodal office for perusing proposal to GOI office. 03 Jul 2023
FP/UK/ROAD/43934/202001 Oct 2022EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 25-5-22 to nodal office for perusing proposal to GOI office. 03 Oct 2022
FP/UK/ROAD/43934/202005 Jul 2023EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 25-5-22 to nodal office for perusing proposal to GOI office. 07 Jul 2023
FP/UK/ROAD/43934/202013 Jul 2023EDS: State Govt. may attend the following shortcomings as per the attachment here. 07 May 2024
FP/UK/ROAD/43934/202006 Dec 2022EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 25-5-22 to nodal office for perusing proposal to GOI office. 10 Feb 2023
FP/UK/ROAD/43934/202027 Apr 2022EDS: State Government is requested to attend the shortcomings as per the letter attached. 13 Jun 2022
FP/UK/ROAD/43934/202030 Jun 2022EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 25-5-22 to nodal office for perusing proposal to GOI office. 16 Sep 2022
FP/UK/ROAD/43934/202008 May 2023EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 25-5-22 to nodal office for perusing proposal to GOI office. 20 May 2023
FP/UK/ROAD/43934/202021 Jun 2022EDS: find the letter attached22 Jun 2022
FP/UK/ROAD/43934/202018 May 2024EDS: please submit hard copy of the compliance for EDS raised by GOI office on dated 25-5-22 to nodal office for perusing proposal to GOI office.23 Sep 2024
FP/UK/ROAD/43934/202023 Jun 2022EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 25-5-22 to nodal office for perusing proposal to GOI office.27 Jun 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/UK/ROAD/43934/202028 Apr 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/UK/ROAD/43934/2020Approved In-PrincipleNo Data