PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
UK-068/2019
1.
Location of the project/Scheme :
Uttarakhand
(i)
State / Union Territory :
Uttarakhand
(ii)
District :
Rudraprayag
(iii)
Forest Division :
Rudraprayag
 (iv)
Area of forest land proposed for diversion (in ha.) :
2.7225
 (v)
Category of the Proposal:
Road
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Rudraprayag
0.7229
Revenue Forest
2
Rudraprayag
1.9996
Village Forest
Total
2.7225
Division 1. : Rudraprayag
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Rudraprayag
2.7225
Total
2.7225
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
2.7225
0.5
Eco 5
Total.
2.7225
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Pinus roxburghii
Chir
44
91
58
6
4
2
2
Quercus leucotricophora
Baanj
6
26
8
0
0
0
3
Rhododendron arboreum
Burash
10
26
9
4
3
0
4
Mycia nagi
Kafal
1
1
1
0
0
0
5
Misc. Species
Kukaat
1
0
0
0
0
0
6
Alnus Nepalensis
Utish
5
9
10
5
3
2
7
Celtis australis
Khadeek
0
0
1
0
0
0
8
Misc. Species
Timla
0
0
2
0
0
0
9
Misc. Species
Ayar
4
0
0
0
0
0
10
Fraxinus Paxiana Ling
Angu
1
1
0
0
0
0
11
Misc. Species
Mahuwa
6
2
1
1
0
0
12
Misc. Species
Thelku
0
1
1
0
0
0
Total
78
157
91
16
10
4
Sub Total (No of Trees.)
356
5.
Working plan prescription for the forest land proposed for diversion :
The area proposed for diversion is Revenue forest. Working Plan for such forests is not prepared.
6.
Brief note on vulnerability of the forest area to erosion :
no erosion pron zone
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.013
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Ghurad, Kakad, Guldar etc.
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
Yes
Details of Protected Area and comments on the impact of Project on the ESZ :
There will be no negative impact of this linear project on wild life sanctuary since the areal distance of this linear project from sanctuary is 13.5 meter and there are agriculture field between proposed project and sanctuary.
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
Yes
Details and comments on the impact of Project on such areas :
There will be no adverse effect on the area wildlife protection related to the construction of this motorway. Also, the work done for the protection of forest and wildlife will be done more effectively.
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
18.36
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
5.445
Chaurash
Khankra
4
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
Joint Report
2
100 tree Estimate
3
Land Shedule
4
NPV
5
Tree Details
6
SIR
7
Aerial distance Certificate
8
CA Map
9
CA Toposheet
10
CA Scheme
11
CA Certificate
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Rudraprayag
198400.00
179099.50
708.230
195
1490.704
12/05/2020
404.137
1086.567
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Rudraprayag
Garhwal
DFO
Yes
One
26/06/2019
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Rudraprayag
Garhwal
DFO
Recommended
The proposal is related with development
Garhwal
CF
Recommended
Recommendation File Part III
Yes
Nodal Officer
Recommended
As per file attached
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Uttarakhand
State Secretary
Recommended
03/12/2019
as per file attached
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Dehradun
Regional Office
8B/UCP/06/197/2019/FC
06/07/2020
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/UK/ROAD/38416/2019
ROAD384162019375
4,136,480.00
2020-07-18
2020-07-27
FP/UK/ROAD/38416/2019
ROAD384162019558
4,136,480.00
4,136,480.00
2020-10-08
PUNBR52020100815419644
Corporation Bank
NEFT/RTGS (Challan)
2020-07-18
2020-07-27
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
5.445
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
5.445
Status of CA Land so identified :
Forest Area
Site Name :
Chaurash
Location Details :
Compartment No. 4, Khankra Range
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Reserve forest
RF
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/UK/ROAD/38416/2019
18 Feb 2021
No Data
As per uploaded detail
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/UK/ROAD/38416/2019
05 Oct 2023
Compliance Details Submitted by User Agency(old)
Proposal No.
Compliance Details submitted on(Date)
Reject Remarks
Reject Date
Uploaded Letter
FP/UK/ROAD/38416/2019
22 Jul 2021
EDS: State Govt. may attend the following shortcomings as per the attachment here
01 Sep 2021
FP/UK/ROAD/38416/2019
27 Jan 2022
EDS: • please submit hard copy of the compliance for EDS raised by reginal office on dated 06-08-21 to nodal office for perusing proposal to RO office.
03 Mar 2022
FP/UK/ROAD/38416/2019
13 Jan 2023
EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 06-08-21 to nodal office for perusing proposal to GOI office.
05 Apr 2023
FP/UK/ROAD/38416/2019
19 May 2023
EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 06-08-21 to nodal office for perusing proposal to GOI office.
20 May 2023
FP/UK/ROAD/38416/2019
24 Mar 2022
EDS: • please submit hard copy of the compliance for EDS raised by reginal office on dated 06-08-21 to nodal office for perusing proposal to RO office.
22 Jun 2022
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/UK/ROAD/38416/2019
30 Jul 2021
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/UK/ROAD/38416/2019
03 Nov 2023
APPROVED
Print
Checklist for State Nodal Officer
×