PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : UK-041/2017
1. Location of the project/Scheme : Uttarakhand
 (i) State / Union Territory : Uttarakhand  (ii) District : Bageshwar  (iii) Forest Division : Bageshwar  (iv) Area of forest land proposed for diversion (in ha.) : 4.4905  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Bageshwar2.8815Reserved Forest
2Bageshwar1.609Village Forest
Total 4.4905
Division 1. : Bageshwar
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Bageshwar4.4905
Total4.4905
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
14.49050.2Eco 5
Total. 4.4905


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Pinus roxburghiichir01871501435330
2Quercus leucotricophorabaanz038000
3Otherskukat0145000
Total 0 204163 14353 30
Sub Total (No of Trees.) 593


5. Working plan prescription for the forest land proposed for diversion : working circle-Chir quality class II/III. P.B. Last and due to public requirements road has been proposed in the forest area.
6. Brief note on vulnerability of the forest area to erosion : area is not prone to soil erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.500
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : wildlife presence is rare in the proposed land to be diverted.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1BageshwarDulam8.9811
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Additional information Details
S. No. DocumentsRemarks
1 CA suitabilty certificate for devinagar (Dhampur)-Tusrera-thanga motor road.
2 CA Scheme certificate for devinagar (Dhampur)-Tusrera-thanga motor road.
3 npv calculation sheet for devinagar (Dhampur)-Tusrera-thanga motor road.

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Bageshwar231000107400726.604153761453.208325/05/20171356.000.00
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
BageshwarNorth KumaunDFOYesOne04/05/2017
 North KumaunCFNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
BageshwarNorth KumaunDFO Recommended
North KumaunCF RecommendedThe Proposal is in Public Interest. As per Proposal population 375 of 3 villages will be benefited hence recommended.Yes
Nodal Officer Recommendedas per file attached
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
UttarakhandState SecretaryRecommended16/01/2018 as per file attached State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
DehradunRegional Office8B/UCP/06/13/2018/FC18/02/2019
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/UK/ROAD/16778/2015ROAD1677820155965,452,949.005,452,949.002019-11-19SBIN219323049666Corporation BankNEFT/RTGS (Challan)2019-03-222019-03-28
FP/UK/ROAD/16778/2015ROAD1677820158121,563,637.00Union Bank Of IndiaNEFT/RTGS (Challan)2024-06-222024-08-30
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 8.981   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)8.981
  Status of CA Land so identified : Non Forest Area   Site Name : Village-Dulam (Kapkot)   Location Details : Village-Dulam (Kapkot)   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
North KumaunBageshwarKapkot87/XXXVI-09Forest/2018-1911 Jun 20198.981
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/UK/ROAD/16778/201517 Feb 2023No DataAs per file attached
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/UK/ROAD/16778/201502 Aug 2024
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/UK/ROAD/16778/201512 May 2023
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/UK/ROAD/16778/2015Approved In-PrincipleNo Data