PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : UK-027/2016
1. Location of the project/Scheme : Uttarakhand
 (i) State / Union Territory : Uttarakhand  (ii) District : Chamoli  (iii) Forest Division : Badrinath,Gopeshwar  (iv) Area of forest land proposed for diversion (in ha.) : 6.45  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Badrinath,Gopeshwar0.4Village Forest
2Badrinath,Gopeshwar0.33Revenue Forest
3Badrinath,Gopeshwar5.72Reserved Forest
Total 6.45
Division 1. : Badrinath,Gopeshwar
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Chamoli6.45
Total6.45
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
16.450.2Eco 5
Total. 6.45


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Pinus roxburghiicheed0424021825
2Quercus leucotricophorabaanj022000
Total 0 4442 218 25
Sub Total (No of Trees.) 140


5. Working plan prescription for the forest land proposed for diversion : Proposed land cover under chir working circle under which resin extensive and removed dead dying disposed trees are recommended.
6. Brief note on vulnerability of the forest area to erosion : No erosion prone area.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.500
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : bear, monkeys, leopard etc.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1Chamolijasyara12.94139,4202 Ma
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Additional information Details
S. No. DocumentsRemarks
1 RO Ojbection remove. date 10-10-2016
2 eds reply 09-11-2017
3 EDS reply date 28-06-2017
4 objection remove date 10-04-2017
5 EDS objection remove. date 28-12-2016
6 revised NPV etc.
7 EDS objection has been removed. date 3-1-2019
8 eds date 14-06-2018
9 eds reply
10 eds reply date 23-08-2018
11 EDS reply date 09-05-2018

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Chamoli8030005147923091.986165739.8031/12/20164250.96132.71
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Badrinath,GopeshwarGarhwalDFOYesOne04/02/2016
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Badrinath,GopeshwarGarhwalDFO RecommendedRecommended in public interest.
GarhwalCF RecommendedRoad is necessary for providing connectivity to the villagers.Yes
Nodal Officer RecommendedAs per file attached
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
UttarakhandState SecretaryRecommended27/04/2016 State Govt. OfficerNo Data