PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : UK-0198/2015
1. Location of the project/Scheme : Uttarakhand
 (i) State / Union Territory : Uttarakhand  (ii) District : Chamoli  (iii) Forest Division : Kedarnath Wild Life Division,Gopeshwar  (iv) Area of forest land proposed for diversion (in ha.) : 2.45  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Kedarnath Wild Life Division,Gopeshwar1.75Reserved Forest
2Kedarnath Wild Life Division,Gopeshwar0.7Revenue Forest
Total 2.45
Division 1. : Kedarnath Wild Life Division,Gopeshwar
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Chamoli2.45
Total2.45
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
12.450.6Eco 5
Total. 2.45


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Rhododendron arboreumBuras01111911
2Misc. SpeciesAyaar, Surai, Ratniyali, Kafal.01016311
3Quercus leucotricophorabaanj0415334
4Alnus Nepalensisootish005500
Total 0 5237 305 6
Sub Total (No of Trees.) 130


5. Working plan prescription for the forest land proposed for diversion : Wildlife habitat improvement, plantations, SMC
6. Brief note on vulnerability of the forest area to erosion : The area is mildly prone to erosion and landslides
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.00
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Leopard, Black Bear, Ghoral, Barking deer, Martens, Wild pig, residents and migratory birds of over 150 species.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : Yes
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1ChamoliPab4.9626
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Additional information Details
S. No. DocumentsRemarks
1

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Chamoli80300051479221031.955247434.3205/12/2015434.320
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Kedarnath Wild Life Division,GopeshwarDirector, Nanda Devi Biosphere Reserve, GopeshwarDFOYesTwo27/02/2015,26/03/2015
 Director, Nanda Devi Biosphere Reserve, CFYesOne27-04-2015
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Kedarnath Wild Life Division,GopeshwarDirector, Nanda Devi Biosphere Reserve, GopeshwarDFO RecommendedThe road will provide motor road connectivity to the village, bringing overall opportunity of better liveihood.
quetiapin ritalin markenavntablet.site quetiapin wirkstoff
Director, Nanda Devi Biosphere Reserve, CF RecommendedThe road will provide motor road connectivity to the village, bringing overall opportunity of better liveihood.Yes
Nodal Officer Recommendedas per file attached
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
UttarakhandState SecretaryRecommended04/06/2015Reccommended State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
DehradunRegional Office8B/UCP/06/116/201504/03/2016
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/UK/ROAD/10123/2015ROAD1012320155052,738,130.00ORBCR52016100300041213Corporation BankNEFT/RTGS (Challan)2016-07-252016-08-06
FP/UK/ROAD/10123/2015ROAD101232015636853,115.00853,115.002023-05-17950467Union Bank Of IndiaNEFT/RTGS (Challan)2023-02-082023-02-08
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 4.9   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)4.9
  Status of CA Land so identified : Non Forest Area   Site Name : Pab   Location Details : Pab Pokhari Chamoli   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
Director, Nanda Devi Biosphere Reserve, GopeshwarKedarnath Wild Life Division,GopeshwarNagnath3826/26-36(2015-2016)Gopeshwar Date 02.04.201602 Apr 20164.9
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/UK/ROAD/10123/201528 Sep 2018No DataAs per file attached
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/UK/ROAD/10123/201530 Sep 2023
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/UK/ROAD/10123/201518 Feb 2022EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 16-01-19 to nodal office for perusing proposal to GOI office. 03 Mar 2022
FP/UK/ROAD/10123/201528 Mar 2022EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 16-1-19 to nodal office for perusing proposal to GOI office.04 Apr 2022
FP/UK/ROAD/10123/201522 Oct 2018EDS: State Government may attend to the shortcomings mentioned in the attached document. 04 Nov 2020
FP/UK/ROAD/10123/201527 Mar 2023EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 16-01-19 to nodal office for perusing proposal to GOI office.05 Apr 2023
FP/UK/ROAD/10123/201529 Dec 2021EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 16-01-19 to nodal office for perusing proposal to GOI office.17 Jan 2022
FP/UK/ROAD/10123/201507 Jun 2023EDS: State Govt. may attend the following shortcomings as per the attachment here 18 Jul 2023
FP/UK/ROAD/10123/201513 Sep 2023EDS: • please submit hard copy of the compliance for EDS raised by GOI office on dated 6-3-23 to nodal office for perusing proposal to GOI office. 21 Sep 2023
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/UK/ROAD/10123/201502 Nov 2018
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/UK/ROAD/10123/201517 Oct 2023APPROVED