PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : TG-045/2016
1. Location of the project/Scheme : Telangana
 (i) State / Union Territory : Telangana  (ii) District : Adilabad  (iii) Forest Division : Kagaznagar  (iv) Area of forest land proposed for diversion (in ha.) : 3.876  (v)

Category of the Proposal: Drinking Water
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Kagaznagar3.876Reserved Forest
Total 3.876
Division 1. : Kagaznagar
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Adilabad3.876
Total3.876
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
13.8760.3Eco 1
Total. 3.876


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Billudu010000
2Misc. SpeciesDumpidi000010
3Misc. SpeciesKodisha000100
4Nalla Maddi000100
5Narayepi001200
6Thada000010
7Teak020100
8Tella Maddi001000
9Misc. SpeciesThruman016200
Total 0 48 72 0
Sub Total (No of Trees.) 21


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : Vulnerable to erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Nil
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : It is a part of notified corridor area of Kawal Tiger Reserve
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 56.559
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
113.876Peddamunagala and Thimmapuram Village of Chandampet MandalWLM Nagarjuna SagarSy.No.169, 139, 147    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 RoFR Certificate
2 Enumeration List

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Adilabad16410091719.3163.761031/05/201300
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
KagaznagarAdilabadDFOYesOne06/09/2016
 AdilabadCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
KagaznagarAdilabadDFO RecommendedRecommended
quetiapin ritalin quetiapin und valdoxan quetiapin wirkstoff
AdilabadCF RecommendedRecommendedYes
Nodal Officer RecommendedRecommended
quetiapin ritalin markenavntablet.site quetiapin wirkstoff
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
TelanganaState SecretaryRecommended20/06/2017 Recommended State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
HyderabadRegional Office4-TSB053/2017-CHN12/07/2017
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/TG/WATER/18192/2016WATER1819220166699,682,984.009,682,984.002018-08-09IDIBH18221262127Corporation BankNEFT/RTGS (Challan)2018-08-032018-08-03
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 6.208   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 2
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)2.332
  Status of CA Land so identified : Forest Area   Site Name : compt.No.84 of Easgaon Beat of Vempally section of Kagaznagar Range of Kagaznagar division of KB Asifabad District   Location Details : compt.No.84 of Easgaon Beat of Vempally section of Kagaznagar Range of Kagaznagar division of KB Asifabad District   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Vempally RFRF
  No. of patches : 2
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
2Block(Polygon)3.876
  Status of CA Land so identified : Forest Area   Site Name : Peddamunigala, Thimmapuram CA site   Location Details : Sy.No.169 of Peddamunigala village, Sy.no. 39,147 of Thimmapuram Village of Neredigommu mandal of Nalgonda district   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
NA
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/TG/WATER/18192/201626 Aug 2022No DataVerfied and accepted
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/TG/WATER/18192/201627 Aug 2022EDS: Please Furnish the replies for the EDS01 Dec 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/TG/WATER/18192/2016Compliance submitted to State Government dt:18.02.202227 Aug 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/TG/WATER/18192/2016Approved In-PrincipleNo Data