PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : TG-021/2018
1. Location of the project/Scheme : Telangana
 (i) State / Union Territory : Telangana  (ii) District : Mancherial  (iii) Forest Division : Bellampally  (iv) Area of forest land proposed for diversion (in ha.) : 1.904  (v)

Category of the Proposal: Transmission Line
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Bellampally1.904Reserved Forest
Total 1.904
Division 1. : Bellampally
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Mancherial1.904
Total1.904
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
11.9040.3Eco 3
Total. 1.904


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Teak372211021350
2OthersBilugu9163200
3OthersVepa5172550
4OthersNemalinara142010
5Eucalyptus070000
6OthersBootankusha020000
7OthersTella Thumma000300
8OthersIriki010000
9OthersRela14151000
10OthersDirshanam010010
11OthersGudipala120000
12Gummadi Teak100000
13OthersTangedu002000
14OthersRaavi000020
15OthersChoppara020000
16OthersKorra maddi020000
17OthersChilakaddi000100
18OthersKanuga523111640
Total 73 313123 4018 0
Sub Total (No of Trees.) 567


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : There will be no noticeable erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Nil
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 32.640
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
113.9Bellampally RFBellampally348    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Enumeration abstract
2 Medicinal Plantation Scheme along the RoW

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Mancherial16128007162447774.933149.320/12/20129.3122.798
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
BellampallyKawal Tiger ReserveDFOYesOne07/09/2018
 Kawal Tiger ReserveCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
BellampallyKawal Tiger ReserveDFO RecommendedRecommended
Kawal Tiger ReserveCF RecommendedRecommended as this project is essential for supply of drinking water to the local peopleYes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
TelanganaState SecretaryRecommended17/12/2018 Recommended State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
HyderabadRegional Office4-TSB141/2018-CHN01/01/2019
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/TG/TRANS/35482/2018TRANS3548220187016,060,400.006,060,400.0017/08/20217187Union Bank Of IndiaUnion Bank Of India (Challan)31/07/202131/07/2021
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 3.9   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)3.9
  Status of CA Land so identified : Forest Area   Site Name : Compt No.348, Bellampally RF of Bellampally Range of Mancherial District   Location Details : Compt No.348, Bellampally RF of Bellampally Range of Mancherial District   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Bellampally RFRF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/TG/TRANS/35482/201827 Sep 2022No DataVerified and Accepted
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/TG/TRANS/35482/201827 Sep 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/TG/TRANS/35482/2018Compliance on Stage-I conditions has been forwarded to State Government on 30.07.2022.27 Sep 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/TG/TRANS/35482/201802 Jan 2023APPROVED