PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : TG-020/2019
1. Location of the project/Scheme : Telangana
 (i) State / Union Territory : Telangana  (ii) District : Jayashankar Bhupalapalli  (iii) Forest Division : Bhupalpally  (iv) Area of forest land proposed for diversion (in ha.) : 8.5  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Bhupalpally4.2339Reserved Forest
Total 4.2339
Division 1. : Bhupalpally
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Jayashankar Bhupalapalli4.2339
Total4.2339
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
14.23390.6Eco 3
Total. 4.2339


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1TeakTectona Grandis85100000
Total 851 00 00 0
Sub Total (No of Trees.) 851


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : No Scope for Soil Erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.5
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Nil
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1Jayashankar BhupalapalliKothapally SM4.2339Sy.No.1196/1 of Kothapally Village of Bhupalpally mandal of Jayashankar Bhupalpally District
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Additional information Details
S. No. DocumentsRemarks
1 CA scheme revised
2 Enumeration list Part-III
3 Certificaes
4 CA NFL Abstract
5 Mitigative measures approved by CWLW
6 Animal Passage plan approved by CWLW
7 Site Suitability certificate
8 Enumeration list abstract
9 CA NFL MAP
10 Collector Undertaking
11 Enumeration list part-II
12 Enumeration list part-II-1
13 Mitigative Plan
14 Enumeration list part-1
15 Enumeration list part-IV
16 Unit Cost and Maintenance of CA NFL compressed
17 EDS reply by DFO

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Jayashankar Bhupalapalli715278346912244.8944660.6607/09/2018660.660
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
BhupalpallyWarangalDFOYesOne18/08/2018
 WarangalCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
BhupalpallyWarangalDFO RecommendedRecommended with the conditions mentioned in the PArt II
WarangalCF RecommendedRecommended for 6.35 Ha only, since this road is fragmenting the forest and causing disturbance to Wildlife and in order to reduce the felling of existing tree growth, the width of the road nlay be limited to 9 meters as per the FDO report in Part II.Yes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
TelanganaState SecretaryRecommended18/12/2019 Recommended State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
HyderabadRegional Office4-TSC160/2019-CHN27/09/2023
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/TG/ROAD/32933/2018ROAD32933201821139,857,073.0039,857,100.0024/03/2025SBINR52025032479471869Union Bank Of IndiaNEFT/RTGS (Challan)NANA
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/TG/ROAD/32933/2018Approved In-PrincipleNo Data