PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : TG-010/2021
1. Location of the project/Scheme : Telangana
 (i) State / Union Territory : Telangana  (ii) District : Mancherial  (iii) Forest Division : Mancherial  (iv) Area of forest land proposed for diversion (in ha.) : 929.29  (v)

Category of the Proposal: Mining
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Mancherial929.29Reserved Forest
Total 929.29
Division 1. : Mancherial
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Mancherial929.29
Total929.29
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
1929.290.4Eco 3
Total. 929.29


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Usiri100000
Total 1 00 00 0
Sub Total (No of Trees.) 1


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : No scope for soil erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Peafowl,
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1128.75Sy.No.394 in Gurajala Village and Sy.No.170 in Budakalan villageBellampally-    View file

Additional information Details
S. No. DocumentsRemarks
1 PCCF to govt letter
2 RoFR certificate
3 IML -1070 ha compliance conditions
4 CA NFL 28-75 Ha map and details
5 Cost Benefit Analysis

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Mancherial3907031764744440.108321067.40531/12/20201067.405189.83
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
MancherialKawal Tiger ReserveDFOYesThree06/08/2020,16/01/2021,23/01/2021
 Kawal Tiger ReserveCFYesOne14/04/2021
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
MancherialKawal Tiger ReserveDFO RecommendedRecommended with the condition in PArt II of DFO
Kawal Tiger ReserveCF RecommendedRecommendedYes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
TelanganaState SecretaryRecommended04/08/2021RecommendedState Govt. OfficerNo Data