1.
Location of the project/Scheme :
Sikkim
(i)
State / Union Territory :
Sikkim
(ii)
District :
Namchi
(iii)
Forest Division :
South Territorial
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.8376
 (v)
Category of the Proposal:
Road
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
South Territorial
0.8376
Reserved Forest
Total
0.8376
Division 1. : South Territorial
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
South
0.8376
Total
0.8376
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.8376
0.7
Eco 4
Total.
0.8376
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Castanopsis Tribuloides
Katus
1
1
1
1
1
2
2
Others
Kharaney
1
1
1
1
1
5
3
Others
Kholmey
0
0
0
0
1
1
4
Alnus Nepolensis
Uttish
1
1
1
1
4
6
5
Others
Angeri
0
0
0
0
0
2
6
Others
Pipli
0
0
0
0
0
1
7
Betula Cylindrostachys
Saur
0
0
0
0
1
0
Total
3
3
3
3
8
17
Sub Total (No of Trees.)
37
5.
Working plan prescription for the forest land proposed for diversion :
Toposheet map fir CA area has been generated by Working Plan Cell
6.
Brief note on vulnerability of the forest area to erosion :
The proposed land for the diversion does not form a part of any seriously eroded areas except which is due to natural factors
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.5
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
NA
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
26.38
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
1.675
Rayong
Ravangla
00
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
Joint Certificate
2
Areal Distance Map
3
CA Scheme
4
Site Suitability for CA
5
Cost of cutting felling
6
NPV
7
SIR of DFO T
8
SIT of DFO T
9
CA map
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Namchi
75000
41341
395.6204
84
608.636
31/03/2021
521.14
2.5
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
South Territorial
Territorial
DFO
Yes
One
27/12/2020
Territorial
CF
No
No Data
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
South Territorial
Territorial
DFO
Recommended
Recommendation of DFO T South for the construction of 2 lane specification road with paved shoulder including Tunnel at Rabangla on NH 510 Singtam Tarku Rabongla Legship Gyalshing Package –III Design Chainage from Km 32+500 to Km 33+60
Territorial
CF
Recommended
Recommendation of CF T for the construction of 2 lane specification road with paved shoulder including Tunnel at Rabangla on NH 510 Singtam Tarku Rabongla Legship Gyalshing Package –III Design Chainage from Km 32+500 to Km 33+60
Yes
Nodal Officer
Recommended
Recommendation of Nodal Officer FCA for the construction of 2 lane specification road with paved shoulder including Tunnel at Rabangla on NH 510 Singtam Tarku Rabongla Legship Gyalshing Package –III Design Chainage from Km 32+500 to Km 33+60
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Sikkim
State Secretary
Recommended
15/06/2021
Recommendation of Secretary for the construction of 2 lane specification road with paved shoulder including Tunnel at Rabangla on NH 510 Singtam Tarku Rabongla Legship Gyalshing Package –III Design Chainage from Km 32+500 to Km 33+60
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Kolkata
Regional Office
SK/ROAD-43/2021/FC
20/07/2021
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/SK/ROAD/115744/2020
ROAD1157442020540
3,110,290.00
3,110,290.00
02/09/2021
IBKL210902416355
Union Bank Of India
NEFT/RTGS (Challan)
29/07/2021
30/07/2021
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
1.675
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
1.675
Status of CA Land so identified :
Forest Area
Site Name :
Rayong RF, Rabong T Range
Location Details :
Rayong RF, Rabong T Range
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Rayong RF
RF
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/SK/ROAD/115744/2020
31 Mar 2022
No Data
Verified and proceed
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/SK/ROAD/115744/2020
28 Jun 2022
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/SK/ROAD/115744/2020
Forwarding of compliance report with undertaking by User Agency.
28 Jun 2022
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/SK/ROAD/115744/2020
08 Feb 2023
APPROVED