PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
RJ-083/2021
1.
Location of the project/Scheme :
Rajasthan
(i)
State / Union Territory :
Rajasthan
(ii)
District :
Jaisalmer
(iii)
Forest Division :
Jaisalmer DDP
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.1794
 (v)
Category of the Proposal:
Transmission Line
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Jaisalmer DDP
0.1794
Protected Forest
Total
0.1794
Division 1. : Jaisalmer DDP
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Jaisalmer
0.1794
Total
0.1794
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.1794
0.2
Eco 4
Total.
0.1794
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Others
Tortalis
0
0
0
0
0
3
2
Prasophis sinereria
Khejari
0
0
0
0
0
1
3
Azadirachta Indica
Neem
0
0
0
0
0
1
Total
0
0
0
0
0
5
Sub Total (No of Trees.)
5
5.
Working plan prescription for the forest land proposed for diversion :
Land is part of protected forest along NH 15
6.
Brief note on vulnerability of the forest area to erosion :
The area proposed for diversion is not vulnerable to erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Chinkara, Desert Fox
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
131369
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
0.50
PF
Dabla
02
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
CA Estimate
2
Medicinal plant scheme
3
Details of amount of NPV to be deposited
4
Land suitability
5
Plant list
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Jaisalmer
3840100
19848.829
4326.423
9
4326.350
07/09/2021
3891.60
564.36
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Jaisalmer DDP
Jodhpur
DFO
Yes
One
14/08/2021
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Jaisalmer DDP
Jodhpur
DFO
Recommended
The site is part of ROW of NH 15 and is suitable for diversion, provided it does not come in the GIB Arc & GIB sensitive zone, for . but 1. order of supreme court dated 19.04.2021 in IA No. 85618 of 2020 in writ petition civil no 838 of 2019 must be strictly followed. 2. order of National green tribunal new Dellhi dted 23.12.2020 in must be strictly followed.
Jodhpur
CF
Recommended
Proposal recommended in public interest.
Yes
Nodal Officer
Recommended
The proposal is in public interest.
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Rajasthan
State Secretary
Recommended
18/11/2021
recommended in public interest.
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Jaipur
State Government
1(86)Forest/2021
18/11/2021
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/RJ/TRANS/141834/2021
TRANS1418342021934
538,706.63
538,706.63
10/12/2021
SBIN321344405352
Union Bank Of India
NEFT/RTGS (Challan)
02/12/2021
06/12/2021
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
0.5
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
0.5
Status of CA Land so identified :
Forest Area
Site Name :
Chhod-1 Protected Forest Block
Location Details :
Range Dabla
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Chhod-1
PF
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/RJ/TRANS/141834/2021
03 Jun 2022
No Data
Land detaiis are verified.
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/RJ/TRANS/141834/2021
03 Jun 2022
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/RJ/TRANS/141834/2021
The compliance report is uploaded.
30 Jun 2022
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/RJ/TRANS/141834/2021
20 Jan 2023
APPROVED
Print
Checklist for State Nodal Officer
×