PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : RJ-0140/2021
1. Location of the project/Scheme : Rajasthan
 (i) State / Union Territory : Rajasthan  (ii) District : Dausa  (iii) Forest Division : Dausa Territorial  (iv) Area of forest land proposed for diversion (in ha.) : 3.0207  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Dausa Territorial3.0207Protected Forest
Total 3.0207
Division 1. : Dausa Territorial
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Dausa3.0207
Total3.0207
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
13.02070.01Eco 3
Total. 3.0207


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Othersacacia tortilis01780000
2Acacia Niloticadesi babool050000
3Ailanthus excelsaArdu010000
4OthersBalanites roxburghii0110000
5Albizia ProceraSiras003000
6Acacia leucophloeaRonjh050000
7Cassia FistulaAmaltaas020000
8OthersDhok0330000
9OthersCheela0200000
10Azadirachta IndicaNeem0200000
11OthersKumtha01020000
12Holoptelia integrifoliaChurel0300000
13OthersGurzan0110000
Total 0 4183 00 0
Sub Total (No of Trees.) 421


5. Working plan prescription for the forest land proposed for diversion : Plantation Working Circle
6. Brief note on vulnerability of the forest area to erosion : The terrain is flate & hilly and not vulnerable for soil erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Neel gai ,Jackak,Fox etc
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1DausaGodawas3.020717
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Additional information Details
S. No. DocumentsRemarks
1 Details of amount of Eco-restoration & Protection wall
2 List of trees to be felled
3 DETAILS OF AMOUNT OF NPV TO BE DEPOSITED
4 Gazette Notification
5 Recommendation certificate
6 Land Suitability for NFL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Dausa34266028459.42267.60414119.812926/04/2022178.71960
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Dausa TerritorialJaipurDFOYesOne22/04/2022
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Dausa TerritorialJaipurDFO RecommendedI recommended for acceptance of the proposal in the interest of tourism & employment generation.
JaipurCF RecommendedI recommended for acceptance of the proposal in the interest of tourism & employment generation.Yes
Nodal Officer RecommendedThe proposal is in public interest
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
RajasthanState SecretaryRecommended06/07/2022RecommendedState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
JaipurRegional Office8B-RAJ040/2022-JPR20/07/2022
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/RJ/ROAD/144538/2021ROAD14453820217653,883,945.00691,342.002022-11-07767418Union Bank Of IndiaNEFT/RTGS (Challan)2022-11-012022-11-02
FP/RJ/ROAD/144538/2021ROAD14453820217653,883,945.003,192,603.002022-11-09768846Union Bank Of IndiaNEFT/RTGS (Challan)2022-11-012022-11-02
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 3.0207   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)3.0207
  Status of CA Land so identified : Non Forest Area   Site Name : Village-Godawas   Location Details : Khasra No.115/17, Village-Godawas, Tehsil-Rahuwas, District-Dausa   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
JaipurDausa TerritorialLALSOT115/1703 Oct 20223.0207
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/RJ/ROAD/144538/202117 Nov 2022No DataOkay
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/RJ/ROAD/144538/202114 Sep 2024
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/RJ/ROAD/144538/202117 Nov 2022EDS: Kindly provide information as per attached document08 Feb 2023
FP/RJ/ROAD/144538/202103 Jun 2024EDS: Re alignment is involved in the proposal kindly get approval from IRO08 Jul 2024
FP/RJ/ROAD/144538/202107 Jul 2023EDS: Kindly provide information as per attached document12 Apr 2024
FP/RJ/ROAD/144538/202121 Feb 2023EDS: Kindly find the attached EDS for compliance.19 Jun 2023
FP/RJ/ROAD/144538/202111 Jul 2024EDS: Re alignment is involved in the proposal kindly get approval from IRO22 Aug 2024
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/RJ/ROAD/144538/2021Compliance has been done.18 Nov 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/RJ/ROAD/144538/202105 Nov 2024APPROVED