PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
PB-0190/2022
1.
Location of the project/Scheme :
Punjab
(i)
State / Union Territory :
Punjab
(ii)
District :
Pathankot
(iii)
Forest Division :
Pathankot
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.858
 (v)
Category of the Proposal:
Road
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Pathankot
0.858
Areas notified under Section 4 of the PLPA
Total
0.858
Division 1. : Pathankot
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Pathankot
0.858
Total
0.858
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.858
0.1
Eco 3
Total.
0.858
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Dalburgia Sisoo
SHISHAM
0
1
0
0
0
0
2
Mangifera Indica
Mango
0
0
0
2
1
1
3
Butea Monosperma
Palah
0
1
0
0
0
0
4
Bombax Ceiba
simbal
0
0
0
1
0
0
5
Misc. Species
Misc. species, because of other plants details is not available on portal.
0
1
3
0
0
0
Total
0
3
3
3
1
1
Sub Total (No of Trees.)
11
5.
Working plan prescription for the forest land proposed for diversion :
yes
6.
Brief note on vulnerability of the forest area to erosion :
Their is no any soil erosion with this project.
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
NIL
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
1242819.54
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
1.716
PF
Pathankot
1
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
OBJECTION REMOVED SNO 1
2
SCHEME FOR COMPENSATORY AFFORESTATION
3
Processing fees @ Rs 50 per sqm in Greening Punjab Fund
4
CERTIFICATE FOR MINIMUM USE OF FOREST LAND
5
Toposheet of Project Site and CA Site
6
FRA CERTIFICATE
7
JUSTIFICATION FOR LOCATION THE PROJECT
8
LEGAL STATUS OF FOREST AREA
9
NPV CALCULATION SHEET OF NPV
10
UNDERTAKING FOR PAYMENT OF ADDITIONAL NET PRESENT VALUE OF FOREST AREA
11
UNDERTAKING FOR PAYMENT OF COST OF RESERVE PRICE OF TREES
12
UNDERTAKING NO Stage I approval is pending
13
APPROVED SITE PLAN
14
UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION
15
DFO SITE INSPECTION REPORT
16
Marking list of Species wise class wise enumeration list of trees to be felled
17
Registration Processing fees @ Rs 2000 per proposal
18
UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
19
STATEMENT SHOWING DETAILS OF NON FOREST AREA INVOLVED IN THE PROPOSAL
20
DFO PHOTO PROJECT SITE
21
Jamabandi Project site
22
Objection removed by User agency
23
Land bank ca details of present proposal
24
PART 2 Recommended for approval
25
Item wise Breakup
26
Toposheet ca site
27
DGPS Map for CA Site
28
DGPS PROJECT SITE
29
FORM A PART 1
30
NOC LAND OWING AGENCIES OBJECTION REMOVED SNO 7
31
Land Suitability certificate of CA Site
32
Project Approval
33
DETAIL NOTE OF THE PROJECT
34
PROJECT APPROVAL OBJECTION REMOVED SNO 6
35
DETAIL NOTE OF THE PROJECT OBJECTION REMOVED SNO 3
36
JUSTIFICATION FOR LOCATION THE PROJECT OBJECTION REMOVED SNO 2
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Pathankot
93712
27577.49
806.4588
207
7.363
30/09/2022
780.547
855.72
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Pathankot
Bist circle
DFO
Yes
One
01/11/2022
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Pathankot
Bist circle
DFO
Recommended
Recommended for approval
Bist circle
CF
Recommended
Recommended for approval
Yes
Nodal Officer
Recommended
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Punjab
State Secretary
Recommended
10/03/2023
Public Utility project
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Chandigarh
Regional Office
9-PBB338-2023-CHA
30/08/2023
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/PB/ROAD/115382/2020
ROAD1153822020012
2,064,595.37
2,064,600.00
Union Bank Of India
NEFT/RTGS (Challan)
19/09/2023
19/09/2023
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/PB/ROAD/115382/2020
Approved In-Principle
No Data
Print
Checklist for State Nodal Officer
×