PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : PB-0286/2020
1. Location of the project/Scheme : Punjab
 (i) State / Union Territory : Punjab  (ii) District : Pathankot  (iii) Forest Division : Pathankot  (iv) Area of forest land proposed for diversion (in ha.) : 1.789  (v)

Category of the Proposal: Pipeline
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Pathankot1.789Protected Forest
Total 1.789
Division 1. : Pathankot
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Pathankot1.789
Total1.789
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
11.7890.6Eco 3
Total. 1.789


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1EucalyptusEUC000210
2Greviia Robusta010010
Total 0 10 22 0
Sub Total (No of Trees.) 5


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : Nil
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Nil
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1PathankotDEHRIWAL1.78946//6,13,14,15,16,17,18,
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Patch wise details for Degraded Area (To be earmarked by DFO)
Patch Wise Details
S.no Division Name Patch No. Area(in ha.)Name of PF/RFRangeVillage NameSurvey No.Compartment No./any identification No. KML file of patch
1Pathankot13.578PFDhar KalanUP Sural11
(i). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (ii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iii). Copy of CA scheme details: (iv). Total Financial Outlay for C.A: 2231054 (v). Whether the land identified by User Agency is suitable for CA and from managementpoint of view?: Yes (vi). Copy of certificate regarding suitability of land identified for CA and from management point of view: (vii). Copy of detailed CA scheme including species to be planted,implementing agency,time schedule,cost structure etc.:
Additional information Details
S. No. DocumentsRemarks
1 UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA.pdf
2 UNDERTAKING NO Stage I approval is pending.
3 DETAIL NOTE OF THE PROJECT.
4 DGPS PROJECT SITE.
5 LEGAL STATUS OF FOREST AREA.
6 user agency is Govt
7 Species wise class wise enumeration list of trees to be felled.
8 PHOTOGRAPHS PROJECT SITE .
9 Item wise breakup Annexure A AREA DETAIL .pdf
10 Processing fees @ Rs 50 per sqm in Greening Punjab Fund
11 Registration Processing fees @ Rs 2000 per proposal.
12 UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION.
13 FORM A PART 1 and JUSTIFICATION FOR LOCATION THE PROJECT
14 UNDERTAKING FOR PAYMENT OF ADDITIONAL NET PRESENT VALUE OF FOREST AREA.
15 SCHEME FOR COMPENSATORY AFFORESTATION
16 STATEMENT SHOWING DETAILS OF NON FOREST AREA INVOLVED IN THE PROPOSAL.
17 PWD NOC.
18 DGPS CA site.
19 UNDERTAKING FOR PROVIDE LAND OF NON FOREST EQUIVALENT OF THE FOREST AREA BEING DIVERTED UNDER FCA 1980.
20 Approved Project Map.
21 DFO SITE INSPECTION REPORT.
22 FRA CERTIFICATE UNDERTAKING.
23 PROJECT APPROVAL
24 PART 2 Recommended for approval.
25 LAND SUITABILITY CERTIFICATE BY THE DFO.
26 DGPS MAP DEHRIWAL
27 TOPOSHEET FOR CA SITE
28 Dehriwal Jamabandi
29 TOPOSHEET DIVERTED AREA
30 UNDERTAKING FOR PROVIDE LAND OF NON FOREST EQUIVALENT OF THE FOREST AREA BEING DIVERTED UNDER FCA 1980.
31 Annexure area detail

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Pathankot9371227577.49806.4582077.36330/09/2020780.5478855.72
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
PathankotBist circleDFOYesOne21/12/2020
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
PathankotBist circleDFO Recommended Recommended fof approval
Bist circleCF RecommendedDiversion of 1.789 ha of forest land for lying sewerage Pipeline at Pathankot to Sarna Both Side Km 5 to 6 Pathankot to Dalhousie road Yes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
PunjabState SecretaryRecommended11/06/2021RecommendedState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ChandigarhRegional Office9-PBB374/2021-CHA23/09/2021
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/PB/Pipeline/62937/2020PIPELINE6293720200002,231,054.001,000,000.002021-12-01HDFC233480908853Union Bank Of IndiaNEFT/RTGS (Challan)2021-09-242021-09-27
FP/PB/Pipeline/62937/2020PIPELINE6293720200002,231,054.001,231,054.002021-12-22HDFC235585241198Union Bank Of IndiaNEFT/RTGS (Challan)2021-09-242021-09-27
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/PB/Pipeline/62937/2020Approved In-PrincipleNo Data