PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : PB-07/2022
1. Location of the project/Scheme : Punjab
 (i) State / Union Territory : Punjab  (ii) District : Bathinda  (iii) Forest Division : Bathinda  (iv) Area of forest land proposed for diversion (in ha.) : 0.0055  (v)

Category of the Proposal: Pipeline
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Bathinda0.0055Protected Forest
Total 0.0055
Division 1. : Bathinda
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Bathinda0.0055
Total0.0055
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.00550.4Eco 3
Total. 0.0055


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Misc. Species000000
Total 0 00 00 0
Sub Total (No of Trees.) 0


5. Working plan prescription for the forest land proposed for diversion : No
6. Brief note on vulnerability of the forest area to erosion : Area is not vulnerable to erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : No
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 0.65183
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.100Phul Disty RD Jaude Pul to Railway Line B/sRampuraPhul Disty RD Jaude Pul to Railway Line B/s    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 EDS REPLY DFO BATHINDA LETTER NO. 2293 DATED 28-06-2022
2 CASEWISE LAND BANK DETAIL AND DECLARATION 28-04-2022
3 DFO BATHINDA REPLY LETTER NO. 683 DATED 28-04-2022
4 IRRIGATION DEPARTMENT NOC
5 NON FOREST AREA DETAIL
6 GREENING PUNJAB MISSION FEE
7 PART-I AND JUSTIFICATION
8 CA COST UNDERTAKING
9 USER AGENCY CATEGORY (STATE GOVT.)
10 TECHNICAL APPROVAL
11 AUTHORITY LETTER
12 FOREST AREA DETAIL
13 APPROVED MAP
14 PROJECT SITE PHOTOGRAPH
15 PROJECT SITE DGPS
16 STAGE-I COMPLIANCE PENDING CASES
17 ADDITIONAL NPV COST UNDERTAKING
18 PART-II
19 FRA CERTIFICATE UNDERTAKING
20 NPV COST UNDERTAKING
21 APPLICATION PROCESSING FEES
22 ADMINISTRATIVE APPROVAL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Bathinda3344056621.56365.281374715.39731/12/2019708.1550
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
BathindaFerozepur CircleDFOYesOne20/01/2022
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
BathindaFerozepur CircleDFO RecommendedPROPOSAL IS RECOMMENDED FOR APPROVAL
Ferozepur CircleCF RecommendedRecommendedYes
Nodal Officer RecommendedPublic Utility Project
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
PunjabState SecretaryRecommended20/12/2022Recommended for approval State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ChandigarhState GovernmentFOREST-FCA0FC1B/6/2022-FCA13/12/2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/PB/Pipeline/147293/2021IN-PRINCIPLENo Data