PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : PB-0172/2021
1. Location of the project/Scheme : Punjab
 (i) State / Union Territory : Punjab  (ii) District : Hoshiarpur  (iii) Forest Division : Dasuya  (iv) Area of forest land proposed for diversion (in ha.) : 0.4156  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Dasuya0.208Delisted area from PLPA 1900
Total 0.208
Division 1. : Dasuya
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Hoshiarpur0.208
Total0.208
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.2080Eco 3
Total. 0.208


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Othersnil000000
Total 0 00 00 0
Sub Total (No of Trees.) 0


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : their will be no soil erosion with this project as there will be no mining only stone gurding will be done.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : pig, blue cow, shamber etc
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 857637.55
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
111.039R-IV Karanpur C-10Talwara-2R-IV Karanpur C-10    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Objection Letter with Notification copy 25.08.2022
2 Mining Undertaking 13.05.2022
3 Undertaking of CA, NPV and Addl NPV
4 Undertaking of CLU
5 Project Detail Note
6 DGPS Map of Diverted Land
7 Status of Forest Area
8 Undertaking of FRA
9 Land Suitability Certificate
10 Reg. Non Forest Area
11 Processing Fee
12 PWD NOC
13 Breakup Area
14 Fard English & Punjabi
15 GPM Fees
16 Part-II
17 Part-1, Online Form-1,, Justification and application
18 Site Photo
19 Site Inspection Report
20 Site Plan
21 Under taking of Pending case for Stage 1
22 Forwarding letter
23 For Letter and User Agency letter dt 06/09/2023
24 NOC Regarding Distance 13.05.2022
25 Far letter 13.05.2022
26 CLU undertaking 13.05.2022
27 Notification Regarding Delisted 13.05.2022
28 CA DGPS Map
29 CA Scheme And Estimate
30 PPCB Undertaking and related documents 13.05.2022
31 Objection far letter dated 02.08.2021
32 Revised Site Plan 29.09.2021
33 Revised Breakup Area 29.09.2021
34 Revised Status of forest area 29.09.2021
35 Revised Land Suitability Certificate 29.09.2021
36 Revised Non Forest area 29.09.2021
37 Revised Part-II 29.09.2021
38 Revised undertakings of CA, NPV & Addl. NPV 29.09.2021
39 Revised CA DGPS Map 29.09.2021
40 Revised CA Scheme 29.09.2021
41 Revised Detail Note 29.09.2021
42 Revised CA Estimate 29.09.2021
43 Revised undertaking of FRA certificate 29.09.2021
44 Revised GPM Fee 29.09.2021
45 Revised Form - A & Justification 29.09.2021
46 Revised Site Inspection Report 29.09.2021
47 Revised Minimum Use certificate 29.09.2021
48 Revised CLU Undertaking 29.09.2021
49 Revised Far latter 29.09.2021
50 Revised Diverted area DGPS Map 29.09.2021
51 undertaking of minimum use 07.09.2021
52 Undertaking of PPCB & related documents applied for NOC 07.09.2021
53 Undertaking of Mining NOC and related documents
54 NOC of Wild life 07.09.2021
55 Objection's forwarding letter 07.09.2021
56 Undertaking of Mining NOS and related documents 07.09.2021
57 Undertaking of CLU 07.09.2021
58 CLU certificate 16.05.2023
59 User agency Justification letter 16.05.2023
60 Far letter 16.05.2023
61 Delisted Notification 16.05.2013
62 Reg Mining 16.05.2023
63 PPCB NOC 16.05.2023

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Hoshiarpur33650034683.12288.9258113582.745731/05/2021313.8172.062
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
DasuyaShiwalik CircleDFOYesOne30.06.2021
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
DasuyaShiwalik CircleDFO RecommendedArea required for development of M/s Hill Side Concrete Plant at village Bringali, Khasra No 83/3, 83/4 which is delisted area of Section of 4 PLPA 1900
Shiwalik CircleCF RecommendedRecommended for ApprovalYes
Nodal Officer RecommendedPrivate Project
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
PunjabState SecretaryRecommended17/03/2022Private projectState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ChandigarhRegional Office9-PBB329-2022-CHA07/10/2023
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/PB/Others/142313/2021OTHERS1423132021904767,825.99767,826.002023-11-15235837Union Bank Of IndiaNEFT/RTGS (Challan)NANA
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/PB/Others/142313/2021Approved In-PrincipleNo Data