PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : PB-0183/2020
1. Location of the project/Scheme : Punjab
 (i) State / Union Territory : Punjab  (ii) District : Sangrur  (iii) Forest Division : Sangrur  (iv) Area of forest land proposed for diversion (in ha.) : 0.00384  (v)

Category of the Proposal: Approach Access
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Sangrur0.00384Protected Forest
Total 0.00384
Division 1. : Sangrur
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Sangrur0.00384
Total0.00384
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.003840Eco 1
Total. 0.00384


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Misc. SpeciesMisc000000
Total 0 00 00 0
Sub Total (No of Trees.) 0


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : no vulnerability erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : na
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : Yes
  (a)Details of violation(s): DR 101821
   (b) Period of Work done(year) : 1
   (c) Area of forest land involved in violation (in ha.) : 0.00384
S. No. Name of person responsible for violation Designation & Address of person responsible for violationAction taken against the person responsible for violation
1MOHAMMAD OWAISM S STAR IMPACT PVT LTD MANUFACTURING OF SPORTS SHOES AND SPORTS GOODS IN VILLAGE HAKIMPURA MALERKOTLARANGE OFFICER MALERKOTLA
12. Whether work in violation is still in progres(Yes/No) : No
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 0.62644
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.00384PFMalerkotlaSIRHAND CHOW RD 265 TO 347 B S    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 PART 3
2 Plantation model CA Scheme 4-5-2022
3 Reply Letter of EDS 4-5-2022
4 Balance sheet for CA Plantation -9-5-2022
5 DETAIL OF FOREST AREA
6 PROJECT MAP AND TOPOSHEET
7 collect rate
8 LETTER
9 CLU
10 COST OF PENAL CA
11 APPLICATION
12 new covering letter
13 COST OF CA
14 OBJECITON MOVE LETTER
15 E STEMP 5
16 NET PRESENT VALUE
17 PAYMENT FOR RESERVE PRICE OR TREE
18 PHOTOS
19 AFFIDAVIT
20 DGPS MAP PROJECT SITE
21 GPM FEES
22 JUSTIFICATION FOR ENVIRONMENT
23 LAND SUITBILITY CERTIFICATE
24 MAP 2
25 NOC FIRE SERVIE
26 SALE DEED 1
27 detail of non forest area
28 FARM A
29 NOC PWD
30 UPDATE NON FOREST LAND EQUIVILANT RATE
31 PART 1
32 E STEMP 2
33 E STEMP 4
34 NOC PPCB
35 TOTAL BREAKUP
36 CERTIFICATE
37 CERTIFICATE
38 COST OF TREE STANDING
39 DETAIL NOTE THE PROJECT
40 E STEMP 1
41 FRA CERTIFICATE
42 JAMABANDI
43 JUSTIFICATION FOR LOCATION
44 LOCATION MAP
45 MININUM USE FORST LAND
46 NOC PPCB 1
47 PROCESSING FEES
48 RANGE OFFICER REPORT
49 SALE DEED 3
50 SALE DEED 5
51 SALE DEED 2
52 STEMP 3
53 UNERTAKING
54 SCHEME FOR CA
55 29 NOV PART 2
56 SITE INSPECTION REPORT 29 NOV
57 VIOLATION REPORT 29 NOV
58 Covering letter
59 COVERING LETER
60 project map
61 NOC PWD
62 MAP
63 project is private or govt
64 plantion model for ca
65 jambandi punjabi
66 REPLY LETER 29 NOV
67 addition amount net present value
68 UPDATE PART 2
69 UPDATE LANDSUIBLITY CERTIFIACTE
70 UPDATE PROJECT APPROVAL LETTER
71 DGPS MAP CA AND PENAL SITE
72 UPDATE SITE INSPECTION REPORT
73 UPDATE REPLY LTER
74 UPDATE PLANTION MODEL FOR CA
75 Land Suitability certificate
76 NPV calculation sheet
77 Part II new
78 EDS reply letter 17-3-2023
79 CA estimate and scheme new
80 CA scheme with new wage rates 411
81 Revised NPV Calculation 24-06-24
82 Revised site inspection & Violation Report
83 Reply DFO Letter No. 2354 dated 24-06-24
84 Revised CA Scheme 24-06-2024

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Sangrur502000701252943822240830/06/2006222.4080
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
SangrurSouth CircleDFOYesOne23/09/2020
 South CircleCFNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
SangrurSouth CircleDFO Recommendedno alternative
South CircleCF RecommendedRecommendedYes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
PunjabState SecretaryRecommended25/07/2024RecommendedState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ChandigarhState GovernmentFOREST-FCA0FC2S/79/2020-FCA25/07/2024
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/PB/Approach/45774/2020APPROACH45774202065266,321.0066,321.0021/02/2026HDFCH00817008172Union Bank Of IndiaNEFT/RTGS (Challan)17/02/202620/02/2026
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/PB/Approach/45774/2020IN-PRINCIPLENo Data