Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
PB-0157/2022
1.
Location of the project/Scheme :
Punjab
(i)
State / Union Territory :
Punjab
(ii)
District :
SAS Nagar
(iii)
Forest Division :
SAS Nagar
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.0061
 (v)
Category of the Proposal:
Approach Access
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
SAS Nagar
0.0061
Protected Forest
Total
0.0061
Division 1. : SAS Nagar
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
SAS Nagar
0.0061
Total
0.0061
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.0061
0
Eco 3
Total.
0.0061
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Misc. Species
Misc Species
0
0
0
0
0
0
Total
0
0
0
0
0
0
Sub Total (No of Trees.)
0
5.
Working plan prescription for the forest land proposed for diversion :
As per Working Plan of Forest Division SAS Nagar by GOI Letter no. F.No. 13-6(13)/1997-ROC dated 30-03-2016 (Year 2015-16 to 2025-26)
6.
Brief note on vulnerability of the forest area to erosion :
No this area is not vulnerability of forest area to erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
No
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
80282
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
0.0061
PF
Kharar
Bir Bakarpur
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
EDS Reply
2
CA Scheme
3
NHAI Map With Calculation
4
Authority Letter
5
Annexure Udda
6
Check List
7
Detailed Note
8
Fard Translation
9
Justification for locating the project
10
NHAI Approval Letter
11
Part 1 UA
12
Part 2
13
Proforma
14
Site Inspection Report of Standing Tree
15
Undertaking EC
16
Undertaking for payment of Cost of CA
17
Case Processing Fee
18
Land Suitability Certificate by DFO
19
Part 1 Online UA
20
Site Pic
21
Toposheet
22
Undertaking for providing Non Forest Land equivalent to the Forest aera
23
Certificate Legal Status
24
NOC PUDA
25
Statement showing Details of Forest Area DFO
26
Undertaking for Environment Clearance
27
Undertaking
28
Undertaking for Payment of Penal NPV
29
Action Monitoring Statement
30
Project Report
31
Certificate Legal Status
32
Annexure Adda
33
Certificate for Minimum use of Forest land
34
EDS Reply 25-11-2023
35
DGPS Map CA Site
36
Undertaking FRA
37
Undertakng for Payment of NPV
38
GPM Fees reciept
39
Undertaking for payment of Cost of Penal CA
40
Fard
41
Location Map with Coordinate
42
Breakup of total land
43
Certificate of Incorporation
44
NOC from District Town Planner
45
DGPS Map UA
46
NPV Calculation Sheet as per new rate
47
Forwarding Letter to Nodal officer
48
Site Inspection Report
49
EDS Reply
50
Toposheet UA
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
SAS Nagar
1092.64
2355.07
353.711
234
681.510
31/03/2023
683.643
0
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
SAS Nagar
South Circle
DFO
Yes
One
24/03/2023
South Circle
CF
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
SAS Nagar
South Circle
DFO
Recommended
User Agency is taking permission for the approach access for Diversion of 0.0061 ha. of Forest Land for approach access and exit to project being developed by M/s MOHALI GREENSVILLE INFRA LLP Located on NH 205A Banur – Kharar Road at Village Kailon, District SAS Nagar Mohali , Punjab under Forest Division SAS Nagar. This proposal is forwarding to you for the further actions and recommended for approval.
South Circle
CF
Recommended
Recommended
Yes
Nodal Officer
Recommended
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Punjab
State Secretary
Recommended
12/04/2024
Recommended
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Chandigarh
State Government
FOREST-FCA0F-1/96/2023-FCA
12/04/2024
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/PB/Approach/153066/2022
APPROACH1530662022404
86,124.00
86,124.00
16/04/2024
000146889678
Union Bank Of India
NEFT/RTGS (Challan)
12/04/2024
12/04/2024
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) :
No
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/PB/Approach/153066/2022
02 May 2024
No Data
CA land is not provided.
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/PB/Approach/153066/2022
02 May 2024
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/PB/Approach/153066/2022
Compliance report
03 Jun 2024
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/PB/Approach/153066/2022
03 Jun 2024
APPROVED
Print