PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : PB-0303/2021
1. Location of the project/Scheme : Punjab
 (i) State / Union Territory : Punjab  (ii) District : Tran Taran  (iii) Forest Division : Amritsar  (iv) Area of forest land proposed for diversion (in ha.) : 0.085  (v)

Category of the Proposal: Approach Access
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Amritsar0.085Protected Forest
Total 0.085
Division 1. : Amritsar
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Tran Taran0.085
Total0.085
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.0850.3Eco 3
Total. 0.085


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Prosophis JulifloraMasquite011100
2Misc. SpeciesMisc.010100
Total 0 21 20 0
Sub Total (No of Trees.) 5


5. Working plan prescription for the forest land proposed for diversion : yes
6. Brief note on vulnerability of the forest area to erosion : This area is not vulnerable to erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : No
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 116312
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.2245PFAjnalaLBC RD 133-144 L/s    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Detail of forest area
2 Undertaking of ROB & LPG
3 ADD CA
4 DGPS Map of CA Site
5 DGPS Map of Project Site
6 GPM Fees Slip
7 Undertaking of High Tension Wire
8 Jamabandi with english translation
9 KML file of project
10 LOI
11 Marking list of trees
12 Minimum use of forest land
13 No Such proposal
14 Non forest area involved
15 Part I
16 PPCB NOC
17 Processing fees slip
18 Undertaking by User agency
19 Detail Note on the project
20 Land Suitability certificate
21 Lease Deed
22 Undertaking of Additional CA
23 Undertaking of Additional NPV
24 Undertaking of CA
25 Undertaking of Cost of trees felled
26 Undertaking of FRA with Application
27 Undertaking of Govt. Private Premises
28 Demand letter
29 Part-2
30 Toposheet
31 CA Scheme
32 Photograph
33 Undertaking of Penal CA
34 Undertaking of Toll Plaza
35 Justification of EC
36 Undertaking of NPV and CA
37 Site Inspection Report
38 Undertaking of NPV
39 Undertaking of CLU
40 Undertaking of NFL
41 Item wise breakup
42 Layout plan
43 Reply of Dyalpura dated 28-2-2022
44 Ministry of Road Transport

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Tran Taran50000614771.73913.6743591708.19431/12/20201589.0040
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
AmritsarBist circleDFOYesOne27/01/2022
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
AmritsarBist circleDFO RecommendedThe strip along this road is declared as Protected Forest
Bist circleCF RecommendedRecommended for approval.Yes
Nodal Officer RecommendedPublic Utility Project
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
PunjabState SecretaryRecommended02/05/2022Public Utility ProjectState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ChandigarhState GovernmentFOREST-FCA0FC5A/6/2022-FCA27/04/2022
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/PB/Approach/148917/2021APPROACH1489172021728236,483.00236,483.0010/11/2022770941Union Bank Of IndiaNEFT/RTGS (Challan)17/05/202217/05/2022
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 0.085   (iii). No. of Maintenance years: 15   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)0.085
  Status of CA Land so identified : Non Forest Area   Site Name : NIL   Location Details : NIL   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
Bist circleAmritsarPatti6813 Jul 20200.085
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/PB/Approach/148917/202109 Dec 2022No DataCA land is verified.
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/PB/Approach/148917/202113 Dec 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/PB/Approach/148917/2021Compliance Report08 Jun 2023
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/PB/Approach/148917/202108 Jun 2023APPROVED