PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
PB-0266/2021
1.
Location of the project/Scheme :
Punjab
(i)
State / Union Territory :
Punjab
(ii)
District :
Hoshiarpur
(iii)
Forest Division :
Dasuya
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.014
 (v)
Category of the Proposal:
Approach Access
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Dasuya
0.014
Protected Forest
Total
0.014
Division 1. : Dasuya
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Hoshiarpur
0.014
Total
0.014
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.014
0.6
Eco 3
Total.
0.014
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Eucalyptus
Safeda
0
0
0
1
0
0
2
Terminalia Arjuna
Arjun
0
0
0
0
0
1
Total
0
0
0
1
0
1
Sub Total (No of Trees.)
2
5.
Working plan prescription for the forest land proposed for diversion :
yes
6.
Brief note on vulnerability of the forest area to erosion :
Their is no any soil erosion with this project
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
pig, shamber, etc
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
95568.40
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
0.156
Haler Janardhan Forest
Mukerian
Haler Janardhan Forest
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
CA Balance Sheet ( 04.05.2022)
2
Revised CA Scheme 04.05.2022
3
Revised DGPS Map 04.05.2022
4
Revised Estimate 04.05.2022
5
PWD NOC 04.05.2022
6
Far Letter 04.05.2022
7
Revised Part-2 04.05.2022
8
Objections forwarding letter 15.07.2022
9
Objection Far letter (CF copy) 15.07.2022
10
Part-II
11
Site Photo
12
Marking list
13
Breakup Area
14
CA DGPS Map
15
CA Scheme, Estimate & Tall Plant Estimate
16
Undertaking of Cost of Trees
17
Detail Note
18
Diverted Area DGPS Map
19
Fard in English & Patanama
20
Form - A, Online & Justification
21
Forest Area
22
GPM Fee
23
LOI
24
PWD NOC
25
Undertaking of deposit Land value & Collector Rate copy
26
Site Inspection Report
27
Far letter
28
Undertaking of Stage -I pending
29
CLU
30
Fard in Punjabi
31
Undertaking of FRA
32
Minimum Use Certificate
33
Non Forest Area
34
Site Plan
35
Undertaking of CA, Addl CA, NPV & Addl NPV
36
Undertaking of Toll Plaza
37
Land Suitability Certificate
38
Processing Fee
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Hoshiarpur
336500
34683.12
291.1652
116
583.3204
30/09/2021
548.7457
2.1149
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Dasuya
Shiwalik Circle
DFO
Yes
One
14.10.2021
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Dasuya
Shiwalik Circle
DFO
Recommended
Construction of HPCL At Village Sariana Hajipur to Mansar Road
Shiwalik Circle
CF
Recommended
Recommended for approval.
Yes
Nodal Officer
Recommended
Public Utility Project
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Punjab
State Secretary
Recommended
02/11/2022
Recommended
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Chandigarh
State Government
FOREST-FCA0FC3D/11/2022-FCA
07/10/2022
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/PB/Approach/147021/2021
APPROACH1470212021842
95,568.40
95,568.40
14/11/2022
774822
Union Bank Of India
NEFT/RTGS (Challan)
09/11/2022
10/11/2022
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) :
No
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/PB/Approach/147021/2021
08 Dec 2022
No Data
CA land is not provided.
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/PB/Approach/147021/2021
13 Dec 2022
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/PB/Approach/147021/2021
Compliance report
20 Mar 2023
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/PB/Approach/147021/2021
09 Jun 2023
APPROVED
Print
Checklist for State Nodal Officer
×