PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
PB-09/2022
1.
Location of the project/Scheme :
Punjab
(i)
State / Union Territory :
Punjab
(ii)
District :
Tran Taran
(iii)
Forest Division :
Amritsar
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.0079
 (v)
Category of the Proposal:
Approach Access
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Amritsar
0.0079
Protected Forest
Total
0.0079
Division 1. : Amritsar
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Tran Taran
0.0079
Total
0.0079
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.0079
0
Eco 3
Total.
0.0079
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Acacia Arabica
xgfd
0
0
0
0
0
0
Total
0
0
0
0
0
0
Sub Total (No of Trees.)
0
5.
Working plan prescription for the forest land proposed for diversion :
Yes
6.
Brief note on vulnerability of the forest area to erosion :
Area is not vulnerable to erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
No
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
Yes
(a)Details of violation(s):
Patti Tarn Taran Road 2-3 R/s
(b) Period of Work done(year) :
2
(c) Area of forest land involved in violation (in ha.) :
0.0015
S. No.
Name of person responsible for violation
Designation & Address of person responsible for violation
Action taken against the person responsible for violation
1
Surjeet Singh
Holy city Enclave Patti Tarn Taran road Patti
Damage report issued and Compensation amounting Rupees Two Thousand seven hundred fifty only
12.
Whether work in violation is still in progres(Yes/No) :
No
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
58308
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
0.1
PF
Ajnala
Bhurewal Minor 0 to tail B/s
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
Authority Letter
2
Forest Area Detail
3
Undertaking of CLU and PPCB Noc
4
Photograph
5
Dgps map of Project site with Kml Print
6
Jamabandi with English Translation
7
Cost of Trees Standing in Forest Area
8
Detail Note
9
DGPS Map with CA site Detail
10
GPM Fee Slip
11
Undertaking of Penal CA
12
Processing Fee Slip
13
Certificate for Minimum Use
14
Demand letter
15
Toposheet
16
Item wise Breakup
17
CA Scheme
18
Undertaking of NFL
19
Layout Plan
20
Part-2
21
Toposheet of CA site
22
Reply dated 03-04-2023
23
Land Suitability Ceritificate
24
FRA Certificate
25
NPV
26
Justification for location of the Project
27
Part-1
28
NOC Of PWD with English Translation
29
Processing Fee Slip
30
NPV Sheet
31
Undertaking of NPV
32
Undertaking of Penal NPV
33
No Such Proposal
34
Undertaking of Additional CA
35
Undertaking of Additional NPV
36
Undertaking of CA
37
Undertaking of EC
38
NOC of Fire with English Translation
39
Non forest Area Detail
40
Reply dated 29-11-2022
41
Undertaking of NFL with English Translation
42
Site Inspection Report
43
Voilation Report with DR copy
44
Layout Plan
45
Reply of Holy City
46
Valid License
47
Undertaking of CLU and PPCB
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Tran Taran
500006
14771.73
815.0615
390
1810.84
30/04/2022
1666.716
0
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Amritsar
Bist circle
DFO
Yes
One
17/10/2022
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Amritsar
Bist circle
DFO
Recommended
The Strip along this Road is declared as protected Forest
Bist circle
CF
Recommended
Recommended for approval. As per DFO Amritsar report user agency has been committed IFA 1927 violation this case. because this case is online applied by User Agency on dated 12/01/2022 and damage report has been issued on dated 30/07/2021
Yes
Nodal Officer
Recommended
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Punjab
State Secretary
Recommended
28/10/2024
Recommended
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Chandigarh
State Government
FOREST-FCA0FC5A/30/2022-FCA
28/10/2024
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/PB/Approach/119613/2021
APPROACH1196132021545
65,874.00
65,874.00
Union Bank Of India
NEFT/RTGS (Challan)
14/11/2024
18/11/2024
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/PB/Approach/119613/2021
IN-PRINCIPLE
No Data
Print
Checklist for State Nodal Officer
×