PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
OR-048/2017
1.
Location of the project/Scheme :
Orissa
(i)
State / Union Territory :
Orissa
(ii)
District :
Gajapati
(iii)
Forest Division :
Parlakhemundi
 (iv)
Area of forest land proposed for diversion (in ha.) :
14.019
 (v)
Category of the Proposal:
Transmission Line
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Parlakhemundi
14.012
Khesra Forest
Total
14.012
Division 1. : Parlakhemundi
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Gajapati
14.012
Total
14.012
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
14.012
0.3
Eco 1
Total.
14.012
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Lannea coromandelica
Moi
0
1
1
3
1
1
2
Pterocarpus marsupium
Bija
0
19
11
2
2
3
3
Lagerstroemia parviflora
Sidha
0
2
0
2
1
2
4
Tectona grandis
Teak
0
36
4
2
3
6
5
Terminalia tomentosa
Asana (Sahaj)
0
0
5
2
0
1
6
Mangifera indica
Amba
0
0
0
0
0
3
7
Alangium lamarckii
Ankula
0
1
5
0
0
0
8
Ficus bengalensis
Bara
0
7
0
4
1
23
9
Bauhinia Parviflora
Barada
0
0
1
0
0
0
10
Anacardium Occidentale
Cashew
0
1
1
1
0
1
11
Anogeissus latifolia
Dhau
0
1
1
1
0
1
12
Syzigium Cumini
Jamu
0
0
1
1
1
1
13
Schleichera oleosa
Kusum
0
1
2
0
1
1
14
Madhuca indica
Mahula
0
3
4
5
1
17
15
Azadirachta indica
Neem
0
1
1
0
0
0
16
Shorea robusta
Sal
0
66
6
4
1
0
17
Albizzia lebbeck
Sirisa
0
0
0
0
1
0
Total
0
139
43
27
13
60
Sub Total (No of Trees.)
282
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
During rainy season the forest land subject to soil erosion by water current
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
1
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
NIL
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
25.416
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
30.00
Idongiri RF
Ramagiri
01
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
NIL
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Gajapati
432500
24445
237.6151
6
0
06/04/2018
0
178.071
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Parlakhemundi
Berhampur
DFO
Yes
One
08/03/2018
Berhampur
CF
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Parlakhemundi
Berhampur
DFO
Recommended
Berhampur
CF
Recommended
This Power Transmission Line Project will reduce the burden on 132/33 KV S/s at Mohana grid substation and will improve Power Suply at R.Udayagiri and its adjacent area i.e. Chandragiri, Cheligada, Seranga and Khajuripada. The Chandragiri has potential for tourism development and the adjoining area is rich in cultivation and a developing area, thus it needs uninterrupted power supply to accelerate the growth rate.
Yes
Nodal Officer
Recommended
Recommended for diversion of 14.012 ha of forest land for construction of 132 KV LILO Transmission Line from existing 132 KV Mohana Digapahandi SC Line to proposed 132/33 KV GRID Station under Parlakhemundi Forest Division of Gajapati District, Odisha by M/s Odisha Power Transmission Corporation Ltd for approval under Section 2 of Forest Conservation Act, 1980
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Orissa
State Secretary
Recommended
14/08/2019
Recommended vide letter no 15416 dated 14.08.2019
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Bhubaneswar
Regional Office
5-ORC391/2019-BHU
11/12/2019
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/OR/TRANS/25459/2017
TRANS254592017304
20,184,660.00
20,184,660.00
2020-02-06
UBINR22020060200179043
Corporation Bank
NEFT/RTGS (Challan)
2020-05-01
2020-05-26
FP/OR/TRANS/25459/2017
TRANS254592017487
3,294,500.00
3,294,500.00
2022-12-23
28719
Union Bank Of India
NEFT/RTGS (Challan)
2022-12-07
2022-12-09
FP/OR/TRANS/25459/2017
TRANS254592017002
37,386,589.00
37,386,600.00
2024-06-01
150826425459002
Union Bank Of India
NEFT/RTGS (Challan)
NA
NA
FP/OR/TRANS/25459/2017
TRANS254592017684
1,597,295.00
1,597,300.00
2024-07-15
0471120740715693391
Union Bank Of India
NEFT/RTGS (Challan)
NA
NA
FP/OR/TRANS/25459/2017
TRANS254592017221
16,355,500.00
16,355,500.00
2024-07-29
0471120240729721825
Union Bank Of India
NEFT/RTGS (Challan)
2024-07-20
2024-07-23
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
36
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
36
Status of CA Land so identified :
Forest Area
Site Name :
Manikur UDPF, R. Udayagiri Range
Location Details :
Manikur UDPF, R. Udayagiri Range under Paralakhemundi Forest Division
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Manikur UDPF
RF
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/OR/TRANS/25459/2017
12 Feb 2024
No Data
verify
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/OR/TRANS/25459/2017
The compliance to the conditions imposed by GoI MoEF & CC IRO Bhubaneswar as well as State Govt. is sent herewith vide this office letter No.2416 dated 08.02.2023 for according final approval.
01 Mar 2024
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/OR/TRANS/25459/2017
Approved In-Principle
No Data
Print
Checklist for State Nodal Officer
×